# Neqsim Ageing Life Extension Screening

> Educational ageing-trend and remaining-life screening (Laplace test, Crow-AMSAA fit, failure projection, maintain-vs-replace) plus the installation technical life basis (design life, cut-off, life-limiting populations). USE WHEN: asked whether equipment ages, how long a host or installation can operate, or whether a study horizon fits technical life.

- Skill: `equinor/neqsim-ageing-life-extension-screening-2` (Agent Skill, multi-file: 7 files)
- Install (CLI): `npx get-skill add equinor/neqsim-ageing-life-extension-screening-2`
- Raw SKILL.md: https://api.skillmd.com/api/skills/equinor/neqsim-ageing-life-extension-screening-2/raw
- Safety review: pending
- Works with: Claude Code, Claude.ai, OpenAI Codex
- Category: Coding & Dev Tools
- Author: equinor (https://skillmd.com/u/equinor)
- Updated: 2026-11-14
- Page: https://skillmd.com/skills/equinor/neqsim-ageing-life-extension-screening-2

---


# Ageing and Life-Extension Screening

Use this skill when a maintenance history has to answer a life-extension question: *is this equipment getting worse, and will it still do its job in year N?* It turns a list of corrective-failure dates into a trend verdict, a fitted failure-intensity model, a projection to a target year, and a maintain-versus-replace crossover.

## When to Use

- A life-extension or lifetime-programme decision must be justified from failure history.
- A user asks whether failures are becoming more frequent (ageing) or less frequent (reliability growth).
- A projection is needed of how many failures to expect between today and a required end-of-life year.
- A maintain-versus-replace comparison is needed at screening level.
- A recurring failure has to be characterised across many years of records.
- A study (tie-back, economics, emissions, capacity increase, concept selection) needs a production or operating horizon: establish the technical life basis first (see below).
- A question asks how long an installation or equipment population can operate, or what limits technical life.

## Do NOT Use For

- A single non-repairable item's time-to-failure distribution — that is a lifetime (Weibull) problem, not a point-process problem.
- Structural fatigue or corrosion remaining-life — those need a damage model, not a failure-count trend.
- A qualified life-extension assessment or regulatory submission. This is screening input to one.

## Technical Life Basis (establish this before any study that uses a horizon)

Any study that needs a field life, production horizon, tie-in tail, NPV window or remaining-life statement (tie-back, debottlenecking, capacity increase, concept selection, emissions or economics roll-up) must first establish an explicit **technical life basis** for the host and for each life-limiting equipment population. Do not assume a horizon; read it, state its source, and carry it into the study as an input with a data-gap flag when it is missing.

**Horizons to read and keep separate.** They are different numbers and routinely disagree:

| Horizon | What it is | Typical source |
|---|---|---|
| Design life | Original design basis (often 20-30 years) | Design basis, datasheets |
| Economic cut-off year | Last year with positive production-forecast cash flow | Production forecast / resource report |
| Life-extension programme validity | Date to which the lifetime programme or consent is valid | Lifetime programme, regulator consent |
| Cessation year | Planned decommissioning / cessation of production | Cessation plan; report "not found" if absent |
| Equipment-specific end of life | Design life expiry or inspection-based residual life per population | Integrity records, class/inspection reports |

Report the **extension ratio** (horizon divided by design life). A ratio above 1 means life extension is already assumed by the horizon, so the question is which populations limit it, not whether to extend.

**Limiter classes to screen for every installation.** Rank them by how early their end of life falls against the horizon:

- Dynamic and flexible risers and umbilicals (fatigue and design-life expiry; check whether a replacement programme is approved, deferred or cancelled).
- Station-keeping and marine systems for floating hosts: mooring lines, winches, ballast and bilge pumps, hull condition. Distinguish approved from draft (unapproved) cost cases.
- Export and infield pipelines (design-life expiry year, corrosion and metal-loss status).
- Obsolescence of control, telemetry, safety and electrical systems (vendor support end dates).
- Rotating equipment and compression headroom late in field life (recycle onset, turndown), which limits tail-end tie-in capacity.
- Structural and hull integrity (condition survey required; state when none was read).

**Verdict vocabulary.** Use the verdicts of this skill at installation level as well: `retain`, `retain-with-measures`, `partial-replacement` (name the populations), `replace`, `insufficient-data-for-decision`. Combine them per limiter, e.g. "retain with measures to the cut-off year, with partial replacement of risers".

**Consequences for dependent studies.**

- A tie-back or new-resource study must cap the host tail at the earliest *unmitigated* limiter, not at the cut-off year. State the usable host tail in years from the tie-in start year and list the limiter checks (riser life, pipeline design-life expiry, compression headroom) that must pass before a tie-in is assumed.
- Economics and emissions roll-ups must use the stated horizon and show the sensitivity to the earliest limiter (a truncated-life case).
- Capacity-increase and debottlenecking studies must not recommend capital on a population whose end of life precedes the payback period without flagging it.

**Evidence rules (what may and may not be concluded).**

- Aggregate failure counts that are flat or falling do **not** demonstrate absence of ageing. Say "no ageing trend demonstrated, no cohort or trend analysis run" unless the per-cohort trend with a plant-wide control (see the data-quality gate) has actually been computed.
- A missing hull, mooring or integrity survey is a **data gap**, never an implicit pass.
- A missing cessation year is reported as "not found", never replaced by the design life or by the cut-off year without saying so.
- Record the retrieval date and source of every horizon, since forecasts and programmes are revised.
- The result is screening input; human review is required before it is used in a decision.

**Minimum output block** for any study that uses this basis: horizon table (with sources and dates), extension ratio, ranked limiter list with end-of-life years, per-limiter verdict, usable host tail for tie-ins, the sources not read, and the data gaps.

## The Modelling Trap This Skill Exists to Prevent

A population that is **repaired and returned to service** is a stochastic point process, not a lifetime distribution. Fitting a two-parameter Weibull to the *inter-arrival times* of a repairable system and reporting the shape parameter as "the ageing parameter" is a standard and consequential error: it assumes every repair restores the item to as-good-as-new, which is exactly the assumption a life-extension study must not make.

The correct screening statistic is the trend in the **rate of occurrence of failures (ROCOF)**. This skill uses two independent, complementary tests of that trend so a single statistic cannot carry the conclusion alone.

## Inputs

- `failure_times_years`: corrective-failure times in years measured from the start of the observation window, each in `(0, observation_years]`.
- `observation_years`: length of the observation window in years (time-truncated).
- `target_year_offset`: years from the **end** of the window to the required end-of-life. Observed to 2026, required to 2037 ⇒ `11.0`.
- `population_size`: number of items, used to normalise reported rates (default 1).
- `replacement_cost`, `corrective_cost_per_failure`, `annual_cost_of_ownership`, `discount_rate`: optional economics in one consistent currency unit.

## Outputs

- `laplace_u`, `laplace_verdict`: `deteriorating` / `improving` / `no-significant-trend` / `insufficient-data`.
- `crow_amsaa_beta`, `crow_amsaa_lambda`, `beta_confidence_low`, `beta_confidence_high`.
- `rate_now_per_year`, `rate_at_target_per_year`, `rate_ratio_target_over_now`.
- `expected_failures_to_target`, `expected_failures_if_no_ageing`, `excess_failures_from_ageing`.
- `ageing_verdict`: `significant-ageing` / `ageing-suspected` / `no-ageing-detected` / `improving` / `insufficient-data`.
- `life_extension_verdict`: `replace` / `extend-with-measures` / `extend` / `insufficient-data-for-decision`.
- `replacement_crossover_year`: first year in which cumulative discounted keep-cost exceeds replacement cost, or `None`.
- `assumptions`: the public assumptions actually applied.

## Engineering Method

**Laplace centroid trend test.** For a time-truncated process observed over $T$ with failures at $t_i$,

$$
U = \frac{\bar t - T/2}{T \big/ \sqrt{12 n}}, \qquad \bar t = \frac{1}{n}\sum_{i=1}^{n} t_i
$$

$U$ is approximately standard normal under the no-trend (homogeneous Poisson) null. $U > 1.96$ means failures cluster late in the window — deterioration. $U < -1.96$ means they cluster early — improvement. The statistic is scale-invariant, so the choice of time unit cannot change the verdict.

**Crow-AMSAA / NHPP power-law intensity.** The mean cumulative function is modelled as

$$
N(t) = \lambda t^{\beta}, \qquad \rho(t) = \frac{\mathrm{d}N}{\mathrm{d}t} = \lambda \beta t^{\beta - 1}
$$

with the time-truncated maximum-likelihood estimates

$$
\hat\beta = \frac{n}{\sum_{i=1}^{n} \ln\!\left(T / t_i\right)}, \qquad
\hat\lambda = \frac{n}{T^{\hat\beta}}
$$

$\beta > 1$ is an increasing ROCOF (system-level wear-out), $\beta = 1$ is a homogeneous Poisson process, $\beta < 1$ is reliability growth. The asymptotic standard error of $\hat\beta$ is $\hat\beta/\sqrt{n}$, which gives the reported confidence band. **Ageing is only called `significant-ageing` when the lower confidence bound on $\beta$ exceeds 1** — a point estimate above 1 on a short record is not evidence.

**Projection to the target year.** Expected failures between the end of the window $T$ and the target $T + \Delta$ are $\lambda\big[(T+\Delta)^{\beta} - T^{\beta}\big]$, compared against the no-ageing baseline $\bar\rho \Delta$. The difference is reported as `excess_failures_from_ageing` so the ageing penalty is separated from the base load.

**Maintain-versus-replace crossover.** Year-by-year the projected failure count is costed, an annual ownership cost is added, the stream is discounted, and the first year where the cumulative keep-cost exceeds the replacement cost is reported.

## The Data-Quality Gate (read before trusting any verdict)

The trend statistics assume a **stationary reporting regime**. Every real CMMS record set violates that somewhere, and each violation biases the trend in a predictable direction:

| Artefact | Effect on the trend | Required action |
|---|---|---|
| System migration stamping thousands of legacy records on one date | Huge fake early cluster ⇒ false `improving` | Truncate the series to start after the migration date |
| Tags created mid-window (modification, life-extension project) | Fake late cluster ⇒ false `deteriorating` | Normalise by the exposed population per year, or start the window at the tag creation date |
| A yard stay / shutdown period with no operation | Silent gap ⇒ both tests biased | Subtract the non-operating period from the exposure time |
| Campaign inspections raising a burst of notifications | Fake late cluster | Screen campaign-driven notifications out or treat the campaign as one event |
| Change in notification practice (new work-order regime) | Step change in rate misread as ageing | Compare the item's rate against the *plant-wide* rate as a control |

The last row is the strongest defence: **always compute the same trend on a control population** from the same plant and report both. A rising rate that matches the plant-wide rise is a reporting change, not ageing.

## Python Usage Pattern

```python
from ageing_life_extension_screening import AgeingLifeExtensionModel

model = AgeingLifeExtensionModel()
result = model.evaluate(
    failure_times_years=[2.1, 5.4, 8.8, 11.2, 12.9, 14.1, 15.6, 16.4, 17.2, 17.9],
    observation_years=18.0,      # 2008 -> 2026
    target_year_offset=11.0,     # required to 2037
    population_size=168,
    replacement_cost=1.0e7,
    corrective_cost_per_failure=1.2e5,
    discount_rate=0.07,
)

print(result.laplace_verdict, result.crow_amsaa_beta)
print(result.expected_failures_to_target, result.excess_failures_from_ageing)
print(result.ageing_verdict, result.life_extension_verdict)
```

## Interpreting the Verdicts

| `life_extension_verdict` | Meaning | Typical follow-up |
|---|---|---|
| `extend` | No trend evidence and economics do not favour replacement | Keep the current maintenance concept; re-screen at the next review |
| `extend-with-measures` | Trend or economics give one warning but not both | Strengthen the maintenance concept, add condition monitoring, target the dominant failure mode |
| `replace` | Significant ageing AND the keep-cost crosses replacement cost inside the target horizon | Build a replacement business case |
| `insufficient-data-for-decision` | Fewer than four usable failure records | Report the data gap; do not report a rate |

A `replace` verdict is a *screening* signal. It has to be combined with the consequence side — for a safety-critical element, a barrier-performance and regulatory assessment governs, not the economics.

## Validation Checklist

- [ ] At least four usable corrective failure records, otherwise the verdict is
      `insufficient-data-for-decision` and no rate is reported.
- [ ] The data-quality gate above has been walked: migration date, mid-window tag
      creation, yard stays, and campaign inspections all screened out.
- [ ] The same trend has been computed on a plant-wide control population and both
      are reported.
- [ ] `observation_years` covers operating time only, with non-operating periods
      subtracted.
- [ ] Costs are on one basis (same currency, same year) and the discount rate is stated.
- [ ] The verdict is presented as screening, with the consequence side handled
      separately for safety-critical elements.

## Common Mistakes

| Symptom | Cause | Fix |
| --- | --- | --- |
| Strong `improving` trend with no engineering reason | Legacy records stamped on the migration date | Truncate the series to start after the migration |
| Strong `deteriorating` trend across a whole plant | Notification practice changed, not the equipment | Compare against the plant-wide control rate |
| Rate jumps in one year | A campaign inspection raised a burst of notifications | Treat the campaign as one event or screen it out |
| Availability looks worse than field experience | Non-operating periods counted as exposure | Subtract yard stays from `observation_years` |
| `replace` on a protective function | Economics used alone | Add the barrier-performance and regulatory assessment |

## Related Skills and Agents

- `neqsim-reliability-data-screening` — MTBF / availability once a failure rate is agreed. Use this skill first to establish whether that rate is *constant*; use that skill second to turn it into availability.
- `neqsim-safety-function-coverage-screening` — when the item is a protective function.
- `neqsim-asset-value-npv-screening`, `neqsim-energy-emissions-screening`, `neqsim-capex-opex-screening`, `neqsim-step-out-screening` — take their horizon from the technical life basis, not from an assumed field life.
- `neqsim-reservoir-facility-value-chain` and the tie-in, concept-selection, debottlenecking and capacity agents — cap the host tail at the earliest unmitigated limiter.
- `neqsim-subsea-slot-tee-reuse-inventory` — uses `lifetime_check` (ok / monitor / life-extend / refurbish / replace / data-gap) for reused slots, tees and lines against the tie-in horizon; take the life basis from this skill.
- A private enterprise wrapper (written by the company) — regulatory framing, maintenance/tag-register evidence requirements, safety-critical-element gating, and review handoff.
- A private maintenance-history reader — pulls the corrective-failure history that feeds `failure_times_years`.
- A private RAM policy skill — company acceptance policy on the resulting availability.

## Limitations

- Screening only. Not a qualified life-extension assessment, technical-condition survey, or regulatory submission.
- The NHPP assumes minimal repair; a genuinely as-good-as-new renewal is not represented.
- Verdicts are driven by open thresholds, not by any operator's acceptance criteria.
- No failure-mode resolution: the projection covers all corrective failures together. Split the series by failure mode when one mode dominates.

## References

- ISO 14224, Collection and Exchange of Reliability and Maintenance Data for Equipment.
- NORSOK Z-008, Risk Based Maintenance and Consequence Classification.
- Crow, L. H., Reliability Analysis for Complex, Repairable Systems, in Reliability and
  Biometry, SIAM, 1974 — the Crow-AMSAA / NHPP power-law model.
- Ascher, H., and Feingold, H., Repairable Systems Reliability, Marcel Dekker, 1984 —
  the Laplace trend test and the minimal-repair assumption.
- NeqSim repository: https://github.com/equinor/neqsim