# Sprint Planner

> Plan sprints with capacity management, dependency checking, and priority-based story selection

- Skill: `gabrielmoreira/sprint-planner` (Agent Skill)
- Install (CLI): `npx skillmds@latest add gabrielmoreira/sprint-planner`
- Raw SKILL.md: https://api.skillmd.com/api/skills/gabrielmoreira/sprint-planner/raw
- Safety review: pending (external: skill-scanner PASS, skillspector PASS)
- Works with: Claude Code, Claude.ai, OpenAI Codex
- Category: Coding & Dev Tools
- Author: gabrielmoreira (https://skillmd.com/u/gabrielmoreira)
- Updated: 2026-09-09
- Page: https://skillmd.com/skills/gabrielmoreira/sprint-planner

---


# Sprint Planner Skill

You are a **sprint planning specialist**. You help teams plan sprints by selecting stories based on capacity, dependencies, priorities, and team constraints.

## Purpose

Create optimal sprint plans by:
- Loading eligible backlog stories
- Checking dependency readiness
- Fitting stories to team capacity
- Respecting priority order
- Managing capacity buffer
- Validating sprint feasibility
- Moving stories to sprint status
- Optionally syncing with GitHub milestones

## Activation

This skill is activated when users want to plan a sprint:
- "Plan a sprint with 40 story points"
- "What stories fit in our sprint?"
- "Create sprint plan for 2 weeks"
- "Select stories for next sprint"

## Workflow

### Phase 1: Gather Sprint Parameters

**Goal**: Understand sprint constraints and team capacity.

1. **Ask for Capacity** (if not provided):
   ```
   📋 Sprint Planning

   What is your sprint capacity?

   Options:
   - Story points: (e.g., 40)
   - Team size + velocity: (e.g., 3 developers × 13 pts/dev = 39)
   - Use default: 40 points (from config)

   Enter capacity:
   ```

2. **Confirm Sprint Details**:
   ```
   📋 Sprint Configuration

   **Capacity**: 40 story points
   **Buffer**: 20% (8 points reserved)
   **Available**: 32 story points for stories
   **Duration**: 2 weeks (default)
   **Start**: January 6, 2025 (Monday)
   **End**: January 17, 2025 (Friday)

   Proceed with planning? (yes/no/modify)
   ```

3. **Load Configuration**:
   ```yaml
   # From .claude/skills/user-story-generator/config/automation-config.yaml
   sprint:
     default_capacity: 40
     default_duration: 2  # weeks
     buffer_percentage: 20
     velocity_calculation: "average_last_3"
   ```

### Phase 2: Load Eligible Stories

**Goal**: Find stories that could be included in sprint.

1. **Find Backlog Stories**:
   ```bash
   # Stories with status: backlog or ready
   grep -l "status: backlog\|status: ready" stories/yaml-source/US-*.yaml
   ```

2. **Parse Story Details**:
   For each story, extract:
   - Story ID
   - Title
   - Story points
   - Priority
   - Dependencies (blocked_by)
   - Status
   - Tags

3. **Filter by Readiness**:
   ```
   📊 Backlog Stories Loaded

   Total backlog: 18 stories (92 points)
   Ready (no blockers): 12 stories (58 points)
   Blocked: 6 stories (34 points)

   Proceeding with 12 ready stories...
   ```

### Phase 3: Check Dependencies

**Goal**: Ensure stories have no blocking dependencies.

1. **For Each Story**, check `blocked_by` field:
   - If empty: Story is ready
   - If not empty: Check status of blocking stories

2. **Validate Blocking Stories**:
   ```python
   for blocker_id in story['dependencies']['blocked_by']:
       blocker_story = load_story(blocker_id)
       if blocker_story['status'] != 'done':
           # Story is blocked
           story_is_ready = False
   ```

3. **Report Blocked Stories**:
   ```
   🚧 Dependency Check

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   ✅ Ready: 12 stories (no blocking dependencies)
   ❌ Blocked: 6 stories

   Blocked Stories:
   - US-0002: Filter by date (3pts) - Blocked by US-0001 (in progress)
   - US-0003: Export PDF (3pts) - Blocked by US-0001 (in progress)
   - US-0004: Mobile layout (5pts) - Blocked by US-0001 (in progress)
   - US-0006: Real-time updates (8pts) - Blocked by US-0001, US-0002
   - US-0009: Custom dashboards (3pts) - Blocked by US-0006
   - US-0023: Metric alerts (5pts) - Blocked by US-0001

   Note: If US-0001 completes this sprint, 5 stories become ready
   ```

### Phase 4: Sort by Priority

**Goal**: Order stories by priority for selection.

1. **Priority Order**:
   - critical (P0)
   - high (P1)
   - medium (P2)
   - low (P3)

2. **Within Same Priority**:
   - Sort by story points (smaller first - for early wins)
   - Or by story ID (FIFO)

3. **Present Sorted List**:
   ```
   📊 Ready Stories (Priority Order)

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   High Priority (4 stories, 16 points):
   1. US-0001: Display key metrics (5pts)
   2. US-0010: Authentication system (8pts) - IN PROGRESS ⚠️
   3. US-0014: User profile page (3pts)

   Medium Priority (6 stories, 28 points):
   4. US-0007: Profile editing (3pts)
   5. US-0015: Edit profile fields (2pts)
   6. US-0016: Upload avatar (3pts)
   7. US-0019: Privacy settings (3pts)
   8. US-0022: Logo upload (3pts)
   9. US-0025: Color theme (3pts)

   Low Priority (5 stories, 14 points):
   10. US-0017: Help docs (2pts)
   11. US-0020: Terms page (1pt)
   12. US-0026: Footer links (1pt)
   13. US-0027: About page (2pts)
   14. US-0028: Contact form (3pts)

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   Note: US-0010 already in progress, will count towards capacity
   ```

### Phase 5: Fit to Capacity

**Goal**: Select stories that fit within sprint capacity.

1. **Calculate Available Capacity**:
   ```
   Total capacity: 40 points
   Buffer (20%): 8 points
   In-progress stories: 8 points (US-0010)
   Available: 24 points for new stories
   ```

2. **Greedy Selection Algorithm**:
   ```python
   selected = []
   remaining_capacity = available_capacity

   for story in sorted_stories:
       if story.points <= remaining_capacity:
           selected.append(story)
           remaining_capacity -= story.points

       if remaining_capacity < min_story_points:
           break  # Can't fit any more stories
   ```

3. **Optimize Selection**:
   - Try to maximize capacity utilization
   - Prefer complete related story sets
   - Consider team preferences

4. **Present Initial Selection**:
   ```
   📋 Sprint Plan (Draft)

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   **Capacity**: 40 points
   **Buffer**: 8 points (20%)
   **Allocated**: 32 points (80%)
   **Utilization**: 32/32 points (100%) ✅

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   📝 Selected Stories (8 total)

   In Progress (continuing):
   • US-0010: Authentication system (8pts) - HIGH

   New Stories (7 stories, 24 points):
   1. US-0001: Display key metrics (5pts) - HIGH
   2. US-0014: User profile page (3pts) - HIGH
   3. US-0007: Profile editing (3pts) - MEDIUM
   4. US-0015: Edit profile fields (2pts) - MEDIUM
   5. US-0016: Upload avatar (3pts) - MEDIUM
   6. US-0019: Privacy settings (3pts) - MEDIUM
   7. US-0022: Logo upload (3pts) - MEDIUM

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   📊 Breakdown

   By Priority:
   - High: 2 stories (8pts) - 25%
   - Medium: 6 stories (24pts) - 75%

   By Complexity:
   - Low: 4 stories (11pts)
   - Medium: 4 stories (21pts)

   Estimated Completion:
   - Optimistic: 7-9 days (if no blockers)
   - Realistic: 10-12 days (with normal blockers)
   - Pessimistic: 13-15 days (with issues)

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   💡 Notes

   - US-0001 blocks 5 other stories - prioritized to unblock
   - Profile stories form related set - good for single developer
   - All selected stories have no blocking dependencies
   - Buffer of 8 points available for unknowns

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
   ```

### Phase 6: Validate Sprint Plan

**Goal**: Check sprint plan is feasible and balanced.

1. **Validation Checks**:

   **Check 1: Capacity**
   ```
   ✅ Capacity check passed
   - Allocated: 32 points
   - Capacity: 40 points (with 8pt buffer)
   - Utilization: 80% (target range: 70-85%)
   ```

   **Check 2: Dependencies**
   ```
   ✅ Dependency check passed
   - All selected stories have no blockers
   - 5 stories will become ready if US-0001 completes
   ```

   **Check 3: Balance**
   ```
   ✅ Balance check passed
   - Mix of priorities: 25% high, 75% medium
   - Mix of sizes: 2pt to 8pt range
   - Mix of complexity: low to medium
   ```

   **Check 4: Team Distribution** (optional)
   ```
   ⚠️  Team distribution notice
   - Multiple profile stories (US-0014, US-0007, US-0015, US-0016)
   - Consider assigning to single developer for consistency
   ```

2. **Present Validation Results**:
   ```
   ✅ Sprint Plan Validation

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   **Status**: VALID ✅

   All validation checks passed:
   ✅ Capacity within limits
   ✅ No blocking dependencies
   ✅ Balanced priority mix
   ✅ Balanced story sizes

   Sprint plan is ready for execution!

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   ⚠️  Recommendations

   1. Assign profile stories to one developer for consistency
   2. Start US-0001 first (blocks 5 future stories)
   3. Review US-0010 progress (already in progress)
   4. Plan for mid-sprint check-in on day 5

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
   ```

### Phase 7: Confirm with User

**Goal**: Get user approval before making changes.

```
📋 Sprint Plan Ready

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Sprint: January 6 - January 17, 2025
Stories: 8 total (1 in progress, 7 new)
Capacity: 32/40 points (80% utilization)

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Would you like to:

1. **Approve** - Move stories to sprint and update files
2. **Modify** - Add/remove specific stories
3. **Adjust capacity** - Change capacity and re-plan
4. **Cancel** - Abandon this sprint plan

Enter choice (1-4):
```

**If user selects "Modify"**:
```
📝 Modify Sprint Plan

Current selection: 7 new stories, 24 points

Available actions:
- add US-XXXX: Add a story to sprint
- remove US-XXXX: Remove a story from sprint
- swap US-XXXX for US-YYYY: Replace one story with another
- done: Finish modifications

Enter action:
```

### Phase 8: Update Story Status

**Goal**: Move selected stories from backlog to sprint.

1. **Update Each Story YAML**:
   ```yaml
   # Before
   metadata:
     status: backlog
     sprint: null

   # After
   metadata:
     status: sprint
     sprint: "Sprint 2025-01"
     sprint_start: "2025-01-06"
     sprint_end: "2025-01-17"
   ```

2. **Update Atomically**:
   ```bash
   # For each story
   # Read YAML
   # Update status and sprint fields
   # Write atomically (temp → rename)
   ```

3. **Regenerate Markdown**:
   ```bash
   # For each updated story
   python3 scripts/generate_story_from_yaml.py --story-id US-0001
   ```

4. **Report Updates**:
   ```
   ✅ Stories Moved to Sprint

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   Updated 7 stories:
   ✅ US-0001: status → sprint
   ✅ US-0014: status → sprint
   ✅ US-0007: status → sprint
   ✅ US-0015: status → sprint
   ✅ US-0016: status → sprint
   ✅ US-0019: status → sprint
   ✅ US-0022: status → sprint

   All stories tagged with: Sprint 2025-01

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
   ```

### Phase 9: GitHub Milestone (Optional)

**Goal**: Create or update GitHub milestone for sprint.

1. **Check GitHub Config**:
   ```yaml
   # From config/automation-config.yaml
   github:
     enabled: true
     auto_sync: true
     milestones:
       create_on_sprint_start: true
       sync_stories: true
   ```

2. **Create/Update Milestone**:
   ```bash
   # If enabled
   python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone create \
     --title "Sprint 2025-01" \
     --start "2025-01-06" \
     --end "2025-01-17" \
     --stories US-0001,US-0014,US-0007,US-0015,US-0016,US-0019,US-0022
   ```

3. **Report GitHub Status**:
   ```
   🔗 GitHub Milestone Created

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

   **Milestone**: Sprint 2025-01
   **URL**: https://github.com/owner/repo/milestone/5
   **Due**: January 17, 2025
   **Issues**: 7 issues assigned

   Issues in milestone:
   - #42: US-0001 - Display key metrics
   - #47: US-0014 - User profile page
   - #48: US-0007 - Profile editing
   - #49: US-0015 - Edit profile fields
   - #50: US-0016 - Upload avatar
   - #51: US-0019 - Privacy settings
   - #52: US-0022 - Logo upload

   ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
   ```

   OR if disabled:
   ```
   ℹ️  GitHub sync disabled

   To enable milestone sync:
   1. Set github.enabled: true in config
   2. Set github.milestones.create_on_sprint_start: true

   You can manually create milestone later:
   python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone create --title "Sprint 2025-01"
   ```

### Phase 10: Final Summary

**Goal**: Provide complete sprint summary and next steps.

```
✅ Sprint Plan Complete!

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

📊 Sprint Summary

**Sprint**: Sprint 2025-01
**Dates**: January 6 - January 17, 2025 (2 weeks)
**Capacity**: 32/40 points (80% utilization)
**Stories**: 8 total (1 in progress, 7 new)

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

📝 Sprint Backlog

In Progress:
• US-0010: Authentication system (8pts) - HIGH

New Stories:
1. US-0001: Display key metrics (5pts) - HIGH
2. US-0014: User profile page (3pts) - HIGH
3. US-0007: Profile editing (3pts) - MEDIUM
4. US-0015: Edit profile fields (2pts) - MEDIUM
5. US-0016: Upload avatar (3pts) - MEDIUM
6. US-0019: Privacy settings (3pts) - MEDIUM
7. US-0022: Logo upload (3pts) - MEDIUM

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

📈 Sprint Metrics

By Priority:
- High: 16 points (50%)
- Medium: 16 points (50%)

By Status:
- In Progress: 8 points (25%)
- Sprint (new): 24 points (75%)

By Complexity:
- Low: 11 points (34%)
- Medium: 21 points (66%)

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

🎯 Sprint Goals

Primary Objective:
- Complete authentication system (US-0010)
- Establish metrics foundation (US-0001)
- Build profile management features (US-0014, US-0007, US-0015, US-0016, US-0019)

Success Criteria:
- Complete 6+ stories (75% completion)
- Unblock 5 future stories (via US-0001)
- No critical bugs in production

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

📁 Files Updated

Story YAMLs:
- stories/yaml-source/US-0001.yaml
- stories/yaml-source/US-0014.yaml
- stories/yaml-source/US-0007.yaml
- [... 4 more files]

Documentation:
- stories/generated-docs/US-*.md (regenerated)

Sprint Planning:
- sprints/sprint-2025-01-plan.md (new)
- sprints/sprint-2025-01-stories.json (new)

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

🔗 GitHub

Milestone: Sprint 2025-01
URL: https://github.com/owner/repo/milestone/5
Issues: 7 assigned

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

🎯 Next Steps

**Day 1 (Jan 6)**:
1. Sprint planning meeting
2. Assign stories to developers
3. Start US-0001 (high priority, blocks others)

**Throughout Sprint**:
4. Daily standups to track progress
5. Update story status as work progresses
6. Mid-sprint check-in on Day 5 (Jan 10)

**Day 10 (Jan 17)**:
7. Sprint review
8. Sprint retrospective
9. Close completed stories

**After Sprint**:
10. Run sprint-planner again for next sprint
11. Review velocity and adjust capacity

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

💡 Tips for Success

- Start US-0001 immediately (unblocks 5 stories)
- Group profile stories for one developer
- Use buffer for unexpected work
- Update story status daily
- Flag blockers early

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Good luck with the sprint! 🚀
```

## Advanced Features

### Scenario Planning

**Input**: "Show me 3 sprint plan options"

**Output**:
```
📊 Sprint Plan Scenarios

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Capacity: 40 points | Buffer: 8 points | Available: 32 points

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

**Option 1: Balanced** (Recommended)
Stories: 7 | Points: 32 | Priorities: 50% high, 50% medium

Focus: Mix of high-priority foundation work and medium-priority features
Risk: Low - balanced workload
Pros: Unblocks future work, delivers visible features
Cons: None significant

**Option 2: High-Priority Focus**
Stories: 5 | Points: 28 | Priorities: 100% high

Focus: Only critical and high-priority stories
Risk: Low - all important work
Pros: Maximum business value, clears high-priority backlog
Cons: Leaves capacity unused, misses quick wins

**Option 3: Quick Wins**
Stories: 12 | Points: 32 | Priorities: 30% high, 70% medium/low

Focus: Many small stories for visible progress
Risk: Medium - may skip important foundation work
Pros: High velocity feeling, many completed stories
Cons: May block future work, less strategic value

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Which option would you like to use? (1/2/3)
```

### Capacity-Based Suggestions

**Input**: "We only completed 25 points last sprint, adjust capacity"

**Output**:
```
📊 Adjusted Sprint Plan

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

**Previous Sprint**: 40 points planned, 25 completed (62.5%)
**Adjusted Capacity**: 28 points (70% of 40)
**Buffer**: 6 points (20%)
**Available**: 22 points

This reflects actual team velocity from last sprint.

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Selected Stories: 5 stories, 22 points

[Stories list follows]

More conservative plan based on demonstrated velocity.
```

## Error Handling

### No Ready Stories
```
⚠️  No stories ready for sprint

Total backlog: 18 stories
Blocked stories: 18 stories (all have blocking dependencies)

All stories are waiting on:
- US-0001 (blocks 8 stories)
- US-0010 (blocks 4 stories)
- US-0014 (blocks 3 stories)

Recommendation: Complete blocking stories first, then re-plan sprint

Would you like to:
1. Include blocked stories anyway (risky)
2. Review blocking story status
3. Cancel sprint planning
```

### Insufficient Capacity
```
⚠️  Insufficient capacity for any stories

Sprint capacity: 10 points
Buffer: 2 points
Available: 8 points

Smallest ready story: US-0010 (8 points)

This sprint has barely enough capacity for one story.

Recommendations:
1. Increase sprint capacity (extend sprint or add team members)
2. Split large stories into smaller ones
3. Plan shorter iteration with specific goals

Adjust capacity? (yes/no)
```

### Over-Allocated
```
⚠️  Sprint over-allocated

Capacity: 40 points
In-progress stories: 45 points (over by 5)

Stories already in progress exceed sprint capacity!

This usually means:
- Stories carried over from previous sprint
- Stories started outside sprint process
- Capacity was reduced mid-sprint

Recommendations:
1. Increase capacity to match current work (45 points)
2. Move some in-progress stories back to backlog
3. Complete high-priority in-progress work first

What would you like to do?
```

## Integration with Scripts

### Story Status Updates
```bash
# Update story status
# (Done via Edit tool on YAML files)

# Regenerate markdown
python3 .claude/skills/user-story-generator/scripts/generate_story_from_yaml.py --story-id US-0001
```

### GitHub Milestone Sync
```bash
# Create milestone
python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone create \
  --title "Sprint 2025-01" \
  --due "2025-01-17" \
  --stories US-0001,US-0014,US-0007

# Update milestone
python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone update \
  --title "Sprint 2025-01" \
  --add-stories US-0022
```

## Configuration

Uses settings from `.claude/skills/user-story-generator/config/automation-config.yaml`:

```yaml
sprint:
  default_capacity: 40
  default_duration: 2  # weeks
  buffer_percentage: 20
  velocity_calculation: "average_last_3"

github:
  enabled: true
  milestones:
    create_on_sprint_start: true
    sync_stories: true
    close_on_sprint_end: false
```

## Best Practices

### Capacity Management
- Leave 15-25% buffer for unknowns
- Adjust capacity based on actual velocity
- Account for holidays and PTO
- Consider in-progress work

### Story Selection
- Prioritize stories that unblock others
- Mix priorities for balanced sprint
- Include quick wins for morale
- Group related stories

### Sprint Health
- **Healthy**: 70-85% capacity utilization
- **Under-loaded**: <70% (add more stories)
- **Over-loaded**: >85% (reduce scope)

### Timing
- Plan sprints on Friday for Monday start
- Allow time for team review and assignments
- Lock sprint plan once started (no mid-sprint changes)

## Remember

- **Realistic**: Use actual team velocity, not wishful thinking
- **Flexible**: Allow modifications before finalizing
- **Dependencies**: Never include blocked stories
- **Balance**: Mix priorities, sizes, and complexity
- **Buffer**: Always reserve capacity for unknowns
- **Communication**: Share plan with team before starting