# Feature Decomposition

> Deciding whether a feature should be split at all and, when it should, into what: child features only where they carry independent value someone can state, Tech Features for independently useful engineering outcomes, and below both a flat list of implementation resources with identifiers, dependencies and their own validation. Use when a feature is about to be implemented as one undifferentiated lump, when a small change is being ceremonially split into items nobody needs, when work has to be ordered because parts depend on each other, when two people or two sessions will share the work, or when progress cannot be reported because there is nothing to report progress against. Does not write the plan around the breakdown (feature-implementation-plan), does not track the resulting statuses (feature-progress-tracking), and does not estimate any of it (estimation-under-uncertainty).

- Skill: `robsonkades/feature-decomposition` (Agent Skill, multi-file: 3 files)
- Install (CLI): `npx skillmds@latest add robsonkades/feature-decomposition`
- Raw SKILL.md: https://api.skillmd.com/api/skills/robsonkades/feature-decomposition/raw
- Safety review: pending
- Works with: Claude Code, Claude.ai, OpenAI Codex
- Category: Docs & Writing
- Author: robsonkades (https://skillmd.com/u/robsonkades)
- Updated: 2026-09-17
- Page: https://skillmd.com/skills/robsonkades/feature-decomposition

---


# Feature Decomposition

## Purpose

Decomposition commonly earns its cost through work that can be **validated
independently**, work that must be **ordered** because of a real dependency, and work that will
be **shared** across people or sessions. Outside those, a breakdown is a table of contents for a
change that would have been easier to read as a diff.

The output that always matters is the **resource list**. Child Product/Tech Features above it are
optional and must remain valuable, independently decidable/deliverable, and testable; resources are
what gets implemented, validated and tracked.

## Workflow

1. **Test whether to decompose at all.** If the feature is one resource, say so and produce a
   one-line list. That is a complete answer.
2. **Produce the resource list first**, from the impact map. Each element in the map becomes a
   resource or joins one; nothing in the map is unaccounted for.
   Reuse the current map/scope revision. If none exists, record a minimal source-to-resource
   mapping for the known work; leave material unknowns open rather than inventing files or scope.
3. **Give each resource a `RES-*` identifier, a dependency list and a validation** — the fields are in
   `references/resource-catalogue.md`. A resource with no stated validation is not finished
   being defined.
4. **Create child features only when the grouping adds an independently valuable outcome.** A Product
   Feature uses `PF-*`; a Tech Feature uses `TF-*` and names measurable engineering value.
5. **Keep enabling work as resources by default.** A migration, component, infrastructure change, or
   test harness is `RES-*` unless it independently reduces risk/cost or enables a usable capability
   with its own acceptance. Do not manufacture a Tech Feature from a phase or layer.
6. **Order the resources** by their dependencies, and say where the order is forced versus
   merely convenient.
   Check missing IDs and cycles. A cycle calls for clarifying a shared contract, splitting a
   producer from its consumer, or merging inseparable work; do not invent a linear order over it.
7. **Say why the shape is what it is** — including "not decomposed, because it is one resource".

## When to decompose

| Signal                                                        | Decompose? |
| ------------------------------------------------------------- | ---------- |
| Parts can be validated independently                          | Yes        |
| Parts must be ordered because one produces what another needs | Yes        |
| Parts will be worked by different people or across sessions   | Yes        |
| Part of it could ship without the rest                        | Yes        |
| It is one file, one test, one behaviour                       | No         |
| The split would be by layer for its own sake                  | No         |
| The parts are only separable on paper                         | No         |

Splitting one behaviour across a controller story, a service story and a repository story
produces three items none of which can be validated alone. That is not decomposition; it is
transcription of the layer diagram.

## Decision rules

```text
IF a child cannot state independent product or engineering value and its own acceptance
THEN it is not a child feature; keep its work as RES-* under the parent.

IF a resource has many dependencies
THEN verify each necessary input and distinguish implementation, validation and release order.
     A legitimate integration resource may consume many outputs; count alone does not justify a split.

IF two resources always change together and are always validated together
THEN consider merging unless ownership, staged compatibility or a real handoff requires separation.

IF a resource cannot be validated without another resource existing
THEN say so in its validation, and let the order follow from it.

IF a resource lacks a path to in-scope impact and acceptance
THEN identify the missing mapping or scope decision. One impact entry can justify several
     resources, and one resource can satisfy several entries; counts are not a scope test.

IF a resource is "write the tests"
THEN it is misplaced: tests belong to the resource whose behaviour they establish.
     A separate test resource is legitimate only for shared harness or fixture work.

IF the feature is Light
THEN return one concise resource with its validation when it remains one local outcome.
     If material dependencies or boundaries emerge, report the changed driver for reclassification;
     this analysis does not itself authorize implementation.
```

## Constraints

- **Do not split to look thorough.** Three resources implemented and tracked beat eleven
  resources of which six are one line each.
- **Do not decompose by layer by default.** Decompose by behaviour, and let a behaviour touch
  several layers.
- **Every resource traces to the impact map and to scope.** A resource that traces to neither is
  scope creep with an identifier.
- **Do not estimate here.** Sizes and dates are a separate concern with separate discipline.
- Preserve supplied Java/framework/runtime and compatibility constraints in each affected
  resource. Decomposition does not choose upgrades or a new technical baseline.

## Output

```text
Decomposition   child features and resources | resources only | none
Because         <the signal that decided it>

PF-01  <independently valuable product outcome and BAC-*>
  RES-01  <resource>
  RES-02  <resource>

TF-01  <independently valuable engineering outcome and TC-*>
  RES-03  <resource>

Parent resources (including work not assigned to a child)
  RES-04  <resource>

Dependencies RES-02 needs RES-01's column; RES-03 needs RES-02's contract
Ready first  RES-01, RES-04 (no dependency between them)
Then         RES-02 -> RES-03; RES-04 may proceed independently
```

Execution consumes resource scope, acceptance, ownership and dependencies together. Independence
in the graph permits parallel planning only when shared-file/resource ownership is also resolved.
Before handoff, check scope coverage, unique/stable IDs, an acyclic dependency graph and validation
for each resource; report unresolved dependencies rather than claiming the breakdown ready.