Variance analysis
Decompose variances, set materiality, write the reason for each material movement, and bridge from one figure to the other. This skill helps prepare the analysis; the CA reviews it before it goes into a report, an audit file or a client meeting.
Numbers come from a workbook with formulas (fortax-xlsx-manipulation): the current and comparison
figures are pulled from the trial balances or MIS, and every variance, effect and percentage is a
formula. The narrative quotes those cells; it never recomputes them.
Inputs
- The two sets being compared: current vs previous period (TB or P&L), actual vs budget, actual vs
forecast. Same ledger mapping on both sides — map with
fortax-financial-statementsStep 1 first. - Drivers where available: quantities and rates (sales register by item, purchase register), headcount and salary register, price lists, the list of one-time items.
- The ledgers themselves, to find reasons. A reason is found in the entries, not invented.
Decomposition techniques
Price / volume
The basic decomposition, for revenue, cost of goods and anything expressible as price x volume.
Total variance = Actual - Budget (or Prior)
Volume effect = (Actual volume - Budget volume) x Budget price
Price effect = (Actual price - Budget price) x Actual volume
Mix effect = residual (interaction term), or allocated proportionally
Check: Volume effect + Price effect = Total variance
(when mix is embedded in the price / volume terms)
Three-way (separating mix):
Volume effect = (Actual volume - Budget volume) x Budget price x Budget mix
Price effect = (Actual price - Budget price) x Budget volume x Actual mix
Mix effect = Budget price x Budget volume x (Actual mix - Budget mix)
Example — revenue:
- Budget: 10,000 units at Rs 500 = Rs 50,00,000
- Actual: 11,000 units at Rs 480 = Rs 52,80,000
- Total variance: +Rs 2,80,000 favourable
- Volume effect: +1,000 units x Rs 500 = +Rs 5,00,000 (favourable — sold more units)
- Price effect: -Rs 20 x 11,000 units = -Rs 2,20,000 (adverse — lower average selling price)
- Net: +Rs 2,80,000
Rate / mix
For blended rates across segments with different economics.
Rate effect = Sum of (Actual volume_i x (Actual rate_i - Budget rate_i))
Mix effect = Sum of (Budget rate_i x (Actual volume_i - Expected volume_i at budget mix))
Example — gross margin: product A 60% margin, product B 40%. Budget mix 50:50 -> blended 50%. Actual mix 40:60 -> blended 48%. Mix explains 2 percentage points of margin compression.
Headcount / salary
Total salary variance = Actual salary cost - Budget salary cost
1. Headcount variance = (Actual HC - Budget HC) x Budget average cost
2. Rate variance = (Actual average cost - Budget average cost) x Budget HC
3. Mix variance = level / department mix shift
4. Timing variance = hiring earlier or later than planned (part-period effect)
5. Attrition impact = savings from unplanned exits (partly offset by replacement cost)
In India also separate: annual increments, statutory changes (minimum wage revision, PF wage ceiling, bonus, gratuity valuation), and contract labour moved to or from payroll.
Expense categories
For operating expenses where price / volume does not fit.
Total expense variance = Actual - Budget
1. Headcount-driven (salaries, PF/ESI, staff welfare, recruitment)
2. Volume-driven (freight, packing, commission, payment gateway charges, power)
3. Discretionary (travel, advertisement, events, professional fees)
4. Contractual/fixed (rent, insurance, software subscriptions, AMC)
5. One-time (settlements, write-offs, project costs, penalties)
6. Timing / phasing (spend shifted between periods vs plan; provisions missed or reversed)
Also check in Indian books: GST credit reversed or disallowed and charged to expense, interest and late fee on statutory dues, prior-period items, and year-end provisions booked in one year and not the other.
Materiality and investigation triggers
Setting thresholds
- Financial statement materiality: typically 1-5% of a benchmark (revenue, total assets, profit
before tax) — for audit, use the materiality set under SA 320 in
fortax-audit. - Line size: larger lines get lower % thresholds.
- Volatility: volatile lines may need higher thresholds to avoid noise.
- Decision relevance: what size of variance would change a decision?
Framework
| Comparison | Amount threshold | % threshold | Trigger |
|---|---|---|---|
| Actual vs budget | client-specific | 10% | Either exceeded |
| Actual vs prior period | client-specific | 15% | Either exceeded |
| Actual vs forecast | client-specific | 5% | Either exceeded |
| Month on month | client-specific | 20% | Either exceeded |
| Audit analytical review of TB | Rs 1 lakh (or client-specific) | 20% | Either exceeded |
| Schedule III ratio note | — | 25% change in the ratio | Reason required |
Set amount thresholds for the client's size; common practice 0.5-1% of revenue for P&L lines.
Priority when many variances cross thresholds
- Largest absolute rupee variance — biggest profit impact.
- Largest % variance — may be an error or a process problem.
- Unexpected direction — opposite to trend or expectation.
- New variance — a line that was on track and is now off.
- Growing variance — larger each period.
Narrative for each material variance
[Line item]: [Favourable / Adverse] variance of Rs [amount] ([x]%) vs [comparison] for [period]
Driver: [primary driver]
[2-3 sentences with the business reason, quantifying each contributing factor, citing the ledgers,
invoices or register rows that show it]
Outlook: [One-time / Expected to continue / Improving / Deteriorating]
Action: [None / Monitor / Investigate further / Update forecast / Ask the client]
Quality checklist — every narrative is:
- Specific: names the actual driver, not "higher than expected"
- Quantified: rupee and % impact of each driver
- Causal: why it happened, not just what
- Forward-looking: whether it will continue
- Actionable: follow-up or decision needed
- Concise: 2-4 sentences
- Evidenced: the reason is in the ledgers or documents; if not, it is a question for the client
Anti-patterns to avoid:
- "Revenue was higher than budget due to higher revenue" (circular).
- "Expenses were elevated this period" (which? why?).
- "Timing" without saying what was early or late and when it reverses.
- "One-time" without saying what the item was.
- "Various small items" for a material variance (decompose further).
- Explaining only the largest driver and ignoring offsetting items.
Waterfall (bridge)
Shows how one value gets to another through positive and negative contributors.
Starting value: [budget / prior period]
Drivers: [contributing factors with signed amounts]
Ending value: [actual / current period]
Check: Starting value + sum of drivers = Ending value (a formula cell)
Text waterfall when no chart tool is available:
WATERFALL: Revenue — Q2 FY 2026-27 actual vs budget (Rs lakh)
Q2 budget revenue 1,000.0
|
|--[+] Volume growth (new customers) +80.0
|--[+] Higher sales to existing customers +40.0
|--[-] Price reductions / discounts -20.0
|--[-] Customers lost / lower orders -35.0
|--[+] Exchange gain on export sales +5.0
|--[-] Timing (orders shifted to Q3) -15.0
|
Q2 actual revenue 1,055.0
Net variance: +55.0 (+5.5% favourable)
Bridge reconciliation table:
| Driver | Amount | % of variance | Cumulative |
|---|---|---|---|
| Volume growth | +80.0 | 145% | +80.0 |
| Existing customers | +40.0 | 73% | +120.0 |
| Price reductions | -20.0 | -36% | +100.0 |
| Customers lost | -35.0 | -64% | +65.0 |
| Exchange gain | +5.0 | 9% | +70.0 |
| Timing | -15.0 | -27% | +55.0 |
| Total variance | +55.0 | 100% |
Individual drivers can exceed 100% when there are offsetting items.
Good practice:
- Order drivers from largest positive to largest negative, or in business sequence.
- Keep to 5-8 drivers; group the small ones into "Other".
- The bridge must reconcile (start + drivers = end) — a check cell.
- In a chart, favourable and adverse bars in two distinct colours, with a legend.
- Label each bar with amount and a short description.
- Include a total variance bar.
In Excel, build the bridge as a stacked column chart with an invisible base series, or a native waterfall chart where the Excel version supports it (openpyxl cannot write native waterfall charts; use the stacked-column method).
Budget vs actual vs forecast
Three-way table:
| Metric | Budget | Forecast | Actual | Budget var (Rs) | Budget var (%) | Forecast var (Rs) | Forecast var (%) |
|---|---|---|---|---|---|---|---|
| Revenue | |||||||
| Cost of goods | |||||||
| Gross margin |
When to use each:
- Actual vs budget: annual performance, incentives, board reporting. Budget is set at the start of the year and not changed.
- Actual vs forecast: operational management, emerging issues. Forecast is updated monthly or quarterly.
- Forecast vs budget: how expectations moved since planning; planning accuracy.
- Actual vs prior period: trend, sequential performance; useful where the budget is not meaningful (new business, post-acquisition).
- Actual vs same period last year: growth adjusted for seasonality (festive quarters, March-end loading).
Forecast accuracy
Forecast accuracy = 1 - |Actual - Forecast| / |Actual|
MAPE = average of |Actual - Forecast| / |Actual| across periods
| Period | Forecast | Actual | Variance | Accuracy |
|---|---|---|---|---|
| Apr | ||||
| May | ||||
| Average | MAPE |
Variance trends (systematic bias)
- Consistently favourable: budget may be too conservative.
- Consistently adverse: budget too aggressive, or execution problems.
- Growing adverse: deteriorating performance or unrealistic targets.
- Shrinking: forecast accuracy improving through the year (normal).
- Volatile: unpredictable business or weak forecasting method.
Output
Into the client folder next to the inputs (e.g. <Client>/<FY>/Audit/Variance_Q2_FY2026-27.xlsx):
sheet Data (both sides, mapped), Variance (formulas, threshold flags), Bridge (with chart),
Narratives; and a short summary: verdict first (what moved most and why), then the material variances,
then the questions for the client where the ledgers do not show the reason.