ECSS Structures — Test Evaluation Report (space-systems/ecss/drd-test-evaluation)
Use when the task is producing or reviewing the test evaluation report (TE DRD) for a structural test campaign under ECSS-E-ST-32C Annex P — comparing observed test outcomes to pre-defined objectives and predicted responses, resolving anomalies, assessing post-test article condition, and recording the overall pass/reject conclusion.
Domain quick reference
- Annex P defines the minimum content for a test evaluation report (TE). The report covers every test event in the campaign (static proof, modal survey, random vibration, acoustic, shock, thermal cycling, etc.) and must address each test objective stated in the test specification.
- A test objective is a specific engineering requirement the test was designed to demonstrate. Each objective is assessed individually as met, not met, or partially met before an overall conclusion is drawn.
- Predicted values (frequencies, displacements, stresses, accelerations) are taken from the approved test prediction (TP DRD). Measured responses are compared against predictions within a defined tolerance band. Any measurement that falls outside the band must be recorded as a finding and given an engineering disposition before the test can be accepted.
- An anomaly is any unexpected event, hardware response, or procedural deviation that occurred during the test. Each anomaly receives a formal disposition: resolved (root cause identified, corrective action confirmed), waived (accepted as-is with justification), or open (unresolved — blocks acceptance until closed).
- Post-test article condition covers dimensional, functional, and visual inspection of the test article after the campaign. An article in acceptable condition shows no damage or degradation beyond the pre-agreed limits; conditional means accepted with qualification; not acceptable blocks the evaluation.
Workflow
- Retrieve the approved test specification and test prediction for the campaign. Identify every stated test objective and every predicted response parameter with its tolerance band.
- For each test objective, assign one of three statuses: met (demonstrated with margin), not met (failed to demonstrate), or partial (demonstrated for a subset of conditions or load levels). Record the supporting evidence (channel ID, measurement value, timestamp).
- For each predicted response parameter, compare the measured value to the prediction. Compute the relative deviation. Flag any parameter whose deviation exceeds the tolerance band as outside-prediction; record as within-prediction otherwise. Sum up counts in both bins.
- List every anomaly logged during the test. Assign a disposition to each: resolved, waived, or open. An open anomaly blocks the overall evaluation — it must be closed before the report can reach an accepted conclusion.
- Record the post-test article condition for each article in the campaign: acceptable, conditional, or not acceptable. A not-acceptable condition blocks acceptance.
- Aggregate the findings from steps 2–5. If all objectives are met, no results fall outside prediction, no anomalies are open, and all article conditions are acceptable or conditional, the overall evaluation status is accepted. Any failing condition yields a rejected status with the finding list as supporting evidence.
- Populate the TE DRD sections: scope and objective list, summary of test execution, objective-by-objective assessment table, prediction-vs-measurement table, anomaly log with dispositions, article condition record, and the overall evaluation conclusion with the responsible engineer's sign-off.
Pitfalls
- Conflating "test completed" with "test objective met" — a test can run to completion while failing to demonstrate its stated requirement (e.g., load level was insufficient, instrumentation failed on the critical channel). The objective assessment must be made explicitly, not inferred from completion.
- Treating an open anomaly as minor and proceeding to an accepted conclusion — every open anomaly is a formal block. An anomaly without an engineering disposition cannot be treated as benign.
- Applying the tolerance band only to the peak response and ignoring frequency or phase deviations — for dynamic tests, the tolerance band covers the frequency of peak response as well as its amplitude; both must be within prediction.
- Omitting the post-test condition assessment for articles that showed no visible damage — the condition record is mandatory for every test article, not only for those with suspected damage.
- Carrying a predicted value from an intermediate analysis revision rather than the approved TP DRD — deviations measured against a superseded prediction are not traceable to the approval baseline and must be recomputed against the authorised document.
Behavior contract (gate 3)
The objective assessment, prediction-comparison, anomaly-disposition, and overall-evaluation logic is exercised by the gate 3 contract test: scripts/test_drd_test_evaluation.py against scripts/drd_test_evaluation_logic.py (stdlib unittest, offline). Run: python3 scripts/test_drd_test_evaluation.py
Compliance
- ECSS standards are freely downloadable (ESA); cite the source and paraphrase per standards-map.yaml.
- compliance: STANDARDS-REF, gated: false.
- Primary reference: ECSS-E-ST-32C Annex P (Test Evaluation DRD).