Use when the task is assembling an Interface Identification Document (IID) per ECSS-E-ST-10-24C Annex D — inventorying every interface of a system or equipment item, categorizing each interface by type, assigning maturity levels, recording responsible parties, and verifying that each interface links to a controlling Interface Control Document.
Domain quick reference
- ECSS-E-ST-10-24C Annex D proposes the content structure for an IID: a header block (document ID, item identity, revision status) followed by an interface register in which each row represents one interface and carries the interface ID, name, type, maturity level, responsible party for each side (A-side and B-side), and a reference to the controlling Interface Control Document (ICD).
- Interface types in the register fall into one of seven recognized categories: physical (mechanical mating, connectors, mounting), electrical (power, grounding, bonding), data (digital communication, protocol, bus), RF (radio-frequency signals, waveguides), thermal (heat transfer paths, temperature boundaries), optical (light paths, field-of-view requirements), and fluid (propellant lines, cooling loops). Every interface is categorized into exactly one type before it enters the register; an unrecognized type is rejected.
- Maturity levels track the agreement status of each interface: proposed (identified but not yet negotiated), agreed (both sides have accepted the interface definition), and baselined (formally controlled under change management). An interface advances from proposed to agreed to baselined; the IID makes maturity visible across all interfaces so that gaps are apparent at any review milestone.
- Every interface in the IID must reference a controlling ICD. A TBD or empty ICD reference is a completeness gap, not a valid state, because the IID is the mapping layer between interface identities and their governing documents.
Workflow
- Identify the system or equipment item whose interfaces are to be documented and collect the item's functional and physical boundary description. Confirm the item's identifier and revision level that will appear in the IID header.
- Inventory every candidate interface by enumerating all connection points, signal exchanges, physical attachments, and environmental boundaries between the item and adjacent systems, subsystems, or the external environment.
- For each candidate interface, categorize it as physical, electrical, data, RF, thermal, optical, or fluid. Reject any interface whose type cannot be mapped to one of these seven categories and escalate for clarification before adding it to the register.
- Assign an initial maturity level to each interface: proposed if it has been identified but not yet negotiated, agreed if both responsible parties have accepted the definition, baselined if it is under formal change control. Record the basis for the assigned level.
- Record the responsible party for both the A-side (the item described by the IID) and the B-side (the adjacent system or element). An interface with an unassigned responsible party on either side is incomplete.
- For each interface, enter the reference identifier of the controlling ICD. If no ICD yet exists, record TBD and flag the interface as a completeness gap; do not leave the field blank.
- Run the completeness check: verify that no interface ID appears more than once, that no required field is empty, that all maturity levels and interface types are valid, and that the ratio of TBD ICD references to total interfaces is within the project's accepted gap threshold for the current milestone.
- Collect all completeness gaps and maturity-level summary counts into the IID status section for review. The IID is not ready for milestone submission until all blocking gaps are resolved.
Pitfalls
- Leaving the ICD reference field empty rather than entering TBD: an empty field makes it impossible to distinguish a deliberately open item from a data-entry omission. Always enter TBD explicitly so the gap is visible in the completeness check.
- Assigning a type of "mechanical" or "structural" instead of "physical": the IID register uses "physical" as the canonical type for mechanical and structural interfaces; deviating creates inconsistency with other items in the same program's IID set.
- Treating an interface as baselined before both responsible parties have agreed: the maturity levels are sequential — an interface cannot skip from proposed to baselined without passing through agreed.
- Omitting internal interfaces between subassemblies of the item: the IID scope covers all interfaces that require an ICD, including internal ones that are controlled across sub-element boundaries.
- Recording only the A-side responsible party and leaving B-side blank because "it belongs to another team": both sides must be recorded in the IID regardless of organizational boundaries; accountability gaps become integration risks.
Behavior contract (gate 3)
The interface-type categorization, maturity-level assignment, ICD-linkage check, and collection-level completeness validation logic is exercised by the gate 3 contract test: scripts/test_e1024_iid_guide.py against scripts/e1024_iid_guide_logic.py (stdlib unittest, offline). Run: python3 scripts/test_e1024_iid_guide.py
Compliance
- ECSS standards are freely downloadable (ESA); cite the source and paraphrase per standards-map.yaml.
- compliance: STANDARDS-REF, gated: false.