Mass Budget (vehicle-design/mass-properties/mass-budget)
Use when the task is building the vehicle mass budget at the conceptual level: allocating subsystem masses, applying the growth allowance and contingency margin policy, rolling up the estimated total mass, and checking the margin-backed total against the MTOW target.
Domain quick reference
- The mass budget is the mass breakdown of the vehicle by subsystem (wing, fuselage, empennage, systems, payload, and so on); the rollup is the sum of the subsystem masses in kg.
- Growth allowance is the percentage added to an estimated mass to cover later design refinement; common practice tightens it as the design matures: about 10 percent in the conceptual phase, about 6 percent in the preliminary phase, and about 3 percent in the detailed phase.
- Contingency margin is an extra percentage on top of the growth-allowance total to cover estimation uncertainty.
- Margin-backed total mass: estimated total multiplied by (1 + growth allowance) and then by (1 + contingency margin).
- The MTOW target check subtracts the margin-backed total from the target takeoff mass; a non-negative margin is within target, a negative margin is over target, and the margin percent is relative to the target.
- Mass budget practice sits in the FAR-25 / CS-25 weight and balance context (CG limits and operating weights rely on the budgeted mass).
Workflow
- Collect the subsystem mass estimates in kg, one entry per subsystem.
- Roll up the budget with rollup_mass_budget.
- Select the design phase and get its growth allowance with phase_growth_allowance.
- Apply the growth allowance with apply_growth_allowance and the contingency margin with contingency_mass.
- Check the margin-backed total against the MTOW target with mtow_check and read the verdict before gating the weight control plan.
Pitfalls
- Applying the growth allowance and the contingency margin only to selected subsystems: both apply to the rolled-up total, not per item, unless the item has its own agreed margin.
- Confusing the two margins: growth allowance covers design refinement, contingency covers estimation uncertainty; they are separate percentages.
- Reporting the raw rollup as the budget total: the margin-backed total is what the weight control plan tracks.
- Reading margin percent with the wrong reference: margin percent is relative to the target mass, not to the estimated mass.
- Passing an empty subsystems dict or a negative fraction; the module raises ValueError instead of guessing.
Behavior contract (gate 3)
The rollup, growth allowance, contingency margin, and MTOW target check logic are exercised by the gate 3 contract test: scripts/test_mass_budget.py against scripts/mass_budget_logic.py (stdlib unittest, offline). Run: python3 scripts/test_mass_budget.py