ECSS Commercial EEE Components -- Class 2 Relifing (space-systems/ecss/q6013-class-2-relifing)
Use when the task is the clause 5.3.10 storage question of ECSS-Q-ST-60-13C at the intermediate assurance class: parts bought for a build have sat in store while the build slipped, the period granted when the lot was accepted has run out, and the question is whether the life of those parts can be extended and on what evidence.
Domain quick reference
- An expired lot is neither scrap nor usable. Relifing is the operation that decides which, and it is an operation with an outcome, not a stamp applied to keep the build moving.
- The storage period a lot earned depends on where it actually sat, not on where the procurement paperwork said it would sit. The package family sets a baseline and the graded store scales it, so the same lot earns a long period in dry nitrogen and half of it in controlled ambient.
- A store with no credited factor grants no period at all. That is not a harsh reading: the record then says where the box was, not what the atmosphere did to the leads, and there is nothing to extend. Such a lot goes for re-screening.
- A lot sitting exactly on its permitted period is inside it. The scaling can leave the two sides a few ULP apart, which is representation error rather than an expired lot, and the comparison absorbs it instead of the period being padded.
- The cycle ceiling is checked before any test is considered. A lot that has used its cycles is not relifed however well it tests, because the question at that point is whether the part is still the part that was accepted, and that is a re-screening question.
- The test set is assembled from the lot, not from a fixed list. External visual and solderability are owed by every family, a seal test by a hermetic one, moisture preconditioning by a moisture-sensitive plastic one, and electrical re-verification from the declared cycle onwards. A test that is missing from the record is missing, not passed.
- This class grants one allowance the class above does not: a solderability failure standing alone, on a lot that has not already used the allowance, permits one re-tin and retest. Any other failure, or a solderability failure alongside another, disposes of the lot.
- Each cycle grants less than the one before it, and the decay is what stops a lot being relifed indefinitely a few months at a time. Once the grant falls under the minimum useful extension the lot goes for re-screening rather than being relifed for a fortnight.
Workflow
- Validate the relifing policy: the extension decay, the minimum useful extension, the cycle ceiling, the cycle from which electrical re-verification is owed, and whether the re-tinning allowance is open. A decay above unity or a zero ceiling is refused rather than used.
- Grade the store and resolve the package family, refusing an unregistered environment or family rather than assuming a period that was never granted. A store crediting nothing closes the assessment.
- Scale the baseline period by the graded store and test the elapsed storage against it. A lot inside its period is reported as still in date and nothing further is done to it.
- Check the cycle ceiling before assembling any test set.
- Assemble the test set the lot owes and validate the record against it, refusing a record that carries a test the lot does not owe and reporting every owed test the record does not carry.
- Apply the re-tinning allowance to a lone solderability failure where the allowance is open and unused; report every other failure and close on the failure.
- Compute the extension this cycle grants, compare it against the minimum useful extension, and return the new permitted period with the findings that produced it.
Pitfalls
- Reading the storage period off the package family alone. The family sets the baseline; the store the parts actually sat in is what scales it, and the two are routinely different from the procurement plan.
- Treating an ungraded store as merely a paperwork gap. A period that was never earned cannot be extended, and relifing such a lot puts unexamined leads into the build.
- Testing first and checking the cycle ceiling afterwards. A lot at its ceiling is a re-screening case whatever the tests say, and running them first invites the result to be argued with.
- Reading a missing test as a pass. An owed test absent from the record is the most common way a relifing record reads complete, and it is reported by name rather than inferred.
- Using the re-tinning allowance on a lot with a second failure. The allowance exists for a storage-induced surface condition standing on its own; alongside a seal or visual failure it is covering for something else.
- Granting a fixed extension every cycle. The decay is the mechanism that ends the sequence, and a flat grant relifes a lot forever in small steps.
Behavior contract (gate 3)
The policy validation, the store grading and family lookup, the scaled storage period and its boundary, the cycle ceiling, the assembled test set including the electrical re-verification cycle, the test record validation and missing-test report, the re-tinning allowance, the decaying extension and the minimum useful extension, and the relifing verdict are exercised by the gate 3 contract test: scripts/test_q6013_class_2_relifing.py against scripts/q6013_class_2_relifing_logic.py (stdlib unittest, offline). Run: python3 scripts/test_q6013_class_2_relifing.py
Compliance
- ECSS standards are freely downloadable (ESA); cite the source and paraphrase per standards-map.yaml.
- compliance: STANDARDS-REF, gated: false.