RSS Workflow
Project-manage an RSS submission against its real calendar. Anchor every date to the
current edition's pages; the 2026 dates below are a verified historical snapshot
(source map rows 1-3, checked 2026-07-08), not a promise about 2027.
Where the cycle stands right now (as of 2026-07-08)
- RSS 2026 (22nd edition, Sydney: UTS + ICC) runs July 13-17, 2026 — conference
week starts in days. The submission funnel (abstract Jan 23 → paper Jan 30 →
supplement Feb 6 → invited rebuttal Apr 3 → decisions Apr 27, all AoE) is closed.
- Accepted authors are in final-presentation mode: talk, poster, travel, and artifact
release (
rss-camera-ready, rss-artifact-evaluation).
- Everyone else is planning RSS 2027, whose site, dates, and deadlines were
unposted at check time (待核实). The recent pattern — late-January deadline, July
conference — is a planning hypothesis only.
The robotics year, seen from RSS
RSS shares its authors with three siblings, so choosing RSS is also choosing a slot in
an annual rotation. Approximate recent geometry (verify each venue's live pages):
| Venue |
Typical deadline |
Typical event |
What slipping past RSS costs |
| RSS |
late January |
July |
Next comparable single-track slot is a full year away |
| IROS |
~March |
~October |
Natural catch for a paper 6 weeks short of RSS-ready |
| CoRL |
~June |
~November |
Right jury if the learning story dominates |
| ICRA |
~September |
~May/June |
Broadest program; absorbs systems breadth |
The practical use: a project that misses the January bar honestly should aim at IROS
or CoRL rather than submit thin — RSS's selectivity makes weak submissions expensive
in reviewer goodwill.
Backward plan to a late-January deadline
| Weeks out |
Milestone for a claim-plus-hardware paper |
| 12+ |
Scientific claim fixed in one sentence; evidence plan sized to it |
| 10 |
Hardware trial campaign running; failure attribution logged from day one |
| 6 |
Ablations that isolate the mechanism complete |
| 4 |
Full draft; supplement storyboard; internal red-team read |
| 2 |
Anonymity sweep of PDF and media; OpenReview metadata entered |
| 1 |
Abstract registered; buffer for robot downtime already spent |
| 0 |
Paper in; supplement due one week later — do not design it that week, only pack it |
The one-week paper→supplement gap (2026: Jan 30 → Feb 6) is packing time, not filming
time; footage shot after the deadline cannot support claims already frozen in the PDF.
Conference-week execution (the stage that is live right now)
For teams presenting at the current edition, the final week has its own checklist:
- Confirm the talk slot, format, and timing against the official program page; a
single-track schedule has no parallel-session slack for overruns.
- Load footage locally; conference-venue networks are not a playback plan.
- Push the public artifact release live before the talk — the single-track
audience is the largest referral event the repository will ever get
(
rss-artifact-evaluation).
- Prepare the poster to carry the evidence detail (trial counts, failure
distribution) that the talk compresses away.
- Assign one author to note every hallway objection; those are free previews of the
journal-extension reviews.
RSS 2027 monitoring plan
Nothing about 2027 was posted at check time. Watch these, in this order, starting
early autumn 2026:
- https://roboticsconference.org/ — the banner rebinds to the new edition.
- The RSS Foundation calendar page (roboticsfoundation.org).
- The OpenReview venue namespace for a
RSS/2027 group appearing.
- The CFP page for the new deadline cascade and any format change — the 8-page
ceiling and the two-stage rebuttal are both cycle policies, not fixtures.
Stage-specific traps
- February-March silence: first reviews are not public-scheduled; do not plan
team availability assuming a known release date (待核实 each cycle).
- The rebuttal is conditional: only papers above a first-round threshold are
invited to respond. Plan an April window in calendars without assuming it will be
used (
rss-author-response).
- April 27 → July is short: visa lead times for the host country can exceed the
decision-to-conference gap; start paperwork at submission time for likely-accept
projects.
- No standing editors: the Program Chair and Area Chairs rotate per edition (2026
PC chair: Matei Ciocarlie, Columbia — verified 2026-07-08); never carry a name or a
policy across cycles.
Ownership map for a multi-person campaign
Robotics submissions fail at handoffs; name owners early:
| Workstream |
Single owner for |
| Claim custody |
The one-sentence claim; vetoes scope drift in any section |
| Trial campaign |
Protocol document, ledger integrity, daily campaign log |
| Media |
Footage banking from every session; the supplement cut |
| Anonymity |
The sweep across PDF, video, archive, and OpenReview fields |
| Deadline mechanics |
AoE conversions, form fields, upload confirmations |
Footage banking deserves emphasis: clips must be captured during the campaign,
because the supplement freezes one week after the paper and reshoots after the
paper deadline cannot support frozen claims.
Output format
[Cycle position] planning 2027 / drafting / submitted / rebuttal window / accepted / conference week
[Next hard date] <date + source URL, or 待核实>
[Critical path] <three tasks gating the next stage>
[Fallback venue] IROS / CoRL / ICRA + trigger condition
[Calendar risks] <robot downtime / visa / footage / rebuttal availability>
1---2name: rss-workflow3description: "Use when planning an RSS (Robotics: Science and Systems) campaign end to end — the late-January abstract/paper/supplement cascade, the invited-rebuttal window, late-April decisions, July conference week — and when placing RSS inside the year-round ICRA/IROS/RSS/CoRL robotics deadline calendar."4metadata:5 source: https://skillmd.com/skills/brycewang-stanford/rss-workflow6---78# RSS Workflow910Project-manage an RSS submission against its real calendar. Anchor every date to the11current edition's pages; the 2026 dates below are a verified historical snapshot12(source map rows 1-3, checked 2026-07-08), not a promise about 2027.1314## Where the cycle stands right now (as of 2026-07-08)1516- RSS 2026 (22nd edition, Sydney: UTS + ICC) runs **July 13-17, 2026** — conference17 week starts in days. The submission funnel (abstract Jan 23 → paper Jan 30 →18 supplement Feb 6 → invited rebuttal Apr 3 → decisions Apr 27, all AoE) is closed.19- Accepted authors are in final-presentation mode: talk, poster, travel, and artifact20 release (`rss-camera-ready`, `rss-artifact-evaluation`).21- Everyone else is planning **RSS 2027**, whose site, dates, and deadlines were22 unposted at check time (待核实). The recent pattern — late-January deadline, July23 conference — is a planning hypothesis only.2425## The robotics year, seen from RSS2627RSS shares its authors with three siblings, so choosing RSS is also choosing a slot in28an annual rotation. Approximate recent geometry (verify each venue's live pages):2930| Venue | Typical deadline | Typical event | What slipping past RSS costs |31|---|---|---|---|32| RSS | late January | July | Next comparable single-track slot is a full year away |33| IROS | ~March | ~October | Natural catch for a paper 6 weeks short of RSS-ready |34| CoRL | ~June | ~November | Right jury if the learning story dominates |35| ICRA | ~September | ~May/June | Broadest program; absorbs systems breadth |3637The practical use: a project that misses the January bar honestly should aim at IROS38or CoRL rather than submit thin — RSS's selectivity makes weak submissions expensive39in reviewer goodwill.4041## Backward plan to a late-January deadline4243| Weeks out | Milestone for a claim-plus-hardware paper |44|---|---|45| 12+ | Scientific claim fixed in one sentence; evidence plan sized to it |46| 10 | Hardware trial campaign running; failure attribution logged from day one |47| 6 | Ablations that isolate the mechanism complete |48| 4 | Full draft; supplement storyboard; internal red-team read |49| 2 | Anonymity sweep of PDF and media; OpenReview metadata entered |50| 1 | Abstract registered; buffer for robot downtime already spent |51| 0 | Paper in; supplement due one week later — do not design it that week, only pack it |5253The one-week paper→supplement gap (2026: Jan 30 → Feb 6) is packing time, not filming54time; footage shot after the deadline cannot support claims already frozen in the PDF.5556## Conference-week execution (the stage that is live right now)5758For teams presenting at the current edition, the final week has its own checklist:5960- Confirm the talk slot, format, and timing against the official program page; a61 single-track schedule has no parallel-session slack for overruns.62- Load footage locally; conference-venue networks are not a playback plan.63- Push the public artifact release live *before* the talk — the single-track64 audience is the largest referral event the repository will ever get65 (`rss-artifact-evaluation`).66- Prepare the poster to carry the evidence detail (trial counts, failure67 distribution) that the talk compresses away.68- Assign one author to note every hallway objection; those are free previews of the69 journal-extension reviews.7071## RSS 2027 monitoring plan7273Nothing about 2027 was posted at check time. Watch these, in this order, starting74early autumn 2026:75761. https://roboticsconference.org/ — the banner rebinds to the new edition.772. The RSS Foundation calendar page (roboticsfoundation.org).783. The OpenReview venue namespace for a `RSS/2027` group appearing.794. The CFP page for the new deadline cascade and any format change — the 8-page80 ceiling and the two-stage rebuttal are both cycle policies, not fixtures.8182## Stage-specific traps8384- **February-March silence:** first reviews are not public-scheduled; do not plan85 team availability assuming a known release date (待核实 each cycle).86- **The rebuttal is conditional:** only papers above a first-round threshold are87 invited to respond. Plan an April window in calendars *without* assuming it will be88 used (`rss-author-response`).89- **April 27 → July is short:** visa lead times for the host country can exceed the90 decision-to-conference gap; start paperwork at submission time for likely-accept91 projects.92- **No standing editors:** the Program Chair and Area Chairs rotate per edition (202693 PC chair: Matei Ciocarlie, Columbia — verified 2026-07-08); never carry a name or a94 policy across cycles.9596## Ownership map for a multi-person campaign9798Robotics submissions fail at handoffs; name owners early:99100| Workstream | Single owner for |101|---|---|102| Claim custody | The one-sentence claim; vetoes scope drift in any section |103| Trial campaign | Protocol document, ledger integrity, daily campaign log |104| Media | Footage banking from every session; the supplement cut |105| Anonymity | The sweep across PDF, video, archive, and OpenReview fields |106| Deadline mechanics | AoE conversions, form fields, upload confirmations |107108Footage banking deserves emphasis: clips must be captured *during* the campaign,109because the supplement freezes one week after the paper and reshoots after the110paper deadline cannot support frozen claims.111112## Output format113114```text115[Cycle position] planning 2027 / drafting / submitted / rebuttal window / accepted / conference week116[Next hard date] <date + source URL, or 待核实>117[Critical path] <three tasks gating the next stage>118[Fallback venue] IROS / CoRL / ICRA + trigger condition119[Calendar risks] <robot downtime / visa / footage / rebuttal availability>120```