UIST Workflow
A UIST year is engineered backwards from two fixed points: the paper deadline in late
March and the conference in the fall. Between them sits a pipeline with almost no
slack for hardware failures, video production, or study scheduling. This skill turns
the cycle into a managed project. All dates below are the verified 2026 numbers
(checked 2026-07-08); reopen uist.acm.org/<year>/cfp/ before committing a calendar.
The 2026 reference calendar
| Date (2026) |
Event |
Author obligation |
| Mar 24 |
Abstract deadline (AoE) |
Title, abstract, authors, track metadata in PCS |
| Mar 31 |
Paper deadline (AoE) |
PDF + video figure + supplementary, all anonymous |
| May 28 - Jun 5 |
Rebuttal window |
5,000-character self-contained response |
| Jun 27 |
Notification |
Decisions are conditional on rebuttal-promised changes |
| Jul 24 |
Camera-ready |
TAPS source, alt text, final video, +10% page allowance |
| Nov 2 |
Doctoral Symposium (in person) |
Separate track, separate deadline |
| Nov 2-5 |
Conference, Detroit |
Talk + (typically) live demo of the system |
As of 2026-07-08 the live obligations are the camera-ready chain for accepted papers
and the adjunct tracks (Demos, Posters — deadlines 待核实, read the CFP) for everyone
else; new submissions target the 2027 cycle.
Backwards plan for a systems paper
Work in reverse from the paper deadline; the ordering below is where UIST projects
actually fail, not a generic writing schedule:
- T minus 0-1 weeks — submission mechanics. PCS uploads, anonymity sweeps,
abstract-field consistency (see
uist-submission).
- T minus 1-3 weeks — video figure production. Scripting, capture, edit,
captions, anonymization. The video cannot be shot until the system is stable, and
it competes with the writing for the same people (see
uist-supplementary).
- T minus 3-6 weeks — evaluation. Technical benchmarks and any user study; IRB
approval must predate this window, so file it in the fall.
- T minus 6-10 weeks — feature freeze. Everything demonstrated in the paper
must exist by here. Features added after freeze belong to the next paper.
- T minus 10+ weeks — build. Include one full hardware re-spin or one major
refactor in the estimate, because there will be one.
Owners and risk register
Assign names, not roles, and write the mitigation before the risk fires:
RISK OWNER MITIGATION
Hardware breaks in video week <name> Build two units; film B-roll early
Study participants no-show <name> Over-recruit 30%; pilot in freeze week
Video render/caption pipeline <name> Dry-run export at T-3w with dummy edit
Page-limit overflow (10pp body) <name> Appendix plan agreed at T-4w
Rebuttal week hits a holiday <name> Pre-draft objection playbook (uist-author-response)
Camera-ready owner on vacation <name> TAPS + alt-text buddy named at notification
The two parallel lanes
UIST is one conference with two archival containers, and a healthy group uses both:
- Papers lane (main proceedings): the full pipeline above.
- Adjunct lane (Demos, Posters — separate chairs, separate deadlines, adjunct
proceedings): a rejected paper's system can still appear at the conference as a
demo; early-stage work can test community reaction as a poster; the same work must
not be submitted to both Demos and Posters (the 2026 rule converts it to a demo and
drops the poster). Decide the fallback lane on notification day, not after the
adjunct deadlines pass.
Planning UIST 2027 from a mid-2026 vantage
For teams reading this in the live window (post-notification 2026), the next Papers
deadline is roughly nine months out and the calendar is not yet published (待核实 —
watch the 2027 site from its first announcement). Provisional planning rules that
survive cycle drift:
- Assume the abstract/paper pair lands in late March ± a few weeks and the
conference in the fall; anchor the feature-freeze ten weeks before the assumed
deadline and adjust when the real dates post.
- Anything involving human subjects needs ethics approval filed by roughly
December; anything involving custom hardware needs its final revision ordered
by January (fab and shipping queues do not respect AoE).
- Book video-production capacity — the person, the rig, the edit suite — for
the two pre-deadline weeks now; it is the least substitutable resource in the
pipeline.
- Draft the contribution list before the spring: if you cannot write three
capability claims in January, the project is a 2028 paper wearing a 2027 badge.
The month-by-month cadence (generic UIST year)
| Months before deadline |
Focus |
| 9-7 |
Routing decision, system architecture, ethics filing |
| 7-4 |
Core build; related-work sweep running in parallel |
| 4-2.5 |
Feature freeze; evaluation harness and pilots |
| 2.5-1 |
Studies and technical characterization; paper skeleton |
| 1-0.5 |
Video production; full drafts circulating |
| 0.5-0 |
Submission mechanics only — nothing new enters the paper |
Between cycles
- File a post-mortem within two weeks of notification while reviews are fresh:
which review criticism was predictable at freeze time?
- Convert the submission's infrastructure — build scripts, benchmark harnesses,
capture rigs — into reusable lab property; UIST groups compound or burn out on
exactly this.
- Watch the next edition's site from its first announcement: dates shift by weeks
between editions and the length rules have changed across recent cycles.
Output format
[Cycle target] UIST <year> papers / demos / posters / DS
[Today's phase] build / freeze / evaluation / video / submission / review / rebuttal / camera-ready / conference prep
[Critical path] <the single task that moves the finish date>
[Risk register] top three, each with named owner
[Next fixed date] <date + obligation>
1---2name: uist-workflow3description: Use when planning a UIST cycle end to end — the late-March abstract and paper deadlines, the ten-week build-freeze before video production, the rebuttal window, conditional acceptance, the July camera-ready, adjunct-track parallel lanes, and the November conference — with owners and risk buffers.4metadata:5 source: https://skillmd.com/skills/brycewang-stanford/uist-workflow6---78# UIST Workflow910A UIST year is engineered backwards from two fixed points: the paper deadline in late11March and the conference in the fall. Between them sits a pipeline with almost no12slack for hardware failures, video production, or study scheduling. This skill turns13the cycle into a managed project. All dates below are the verified 2026 numbers14(checked 2026-07-08); reopen `uist.acm.org/<year>/cfp/` before committing a calendar.1516## The 2026 reference calendar1718| Date (2026) | Event | Author obligation |19|---|---|---|20| Mar 24 | Abstract deadline (AoE) | Title, abstract, authors, track metadata in PCS |21| Mar 31 | Paper deadline (AoE) | PDF + video figure + supplementary, all anonymous |22| May 28 - Jun 5 | Rebuttal window | 5,000-character self-contained response |23| Jun 27 | Notification | Decisions are conditional on rebuttal-promised changes |24| Jul 24 | Camera-ready | TAPS source, alt text, final video, +10% page allowance |25| Nov 2 | Doctoral Symposium (in person) | Separate track, separate deadline |26| Nov 2-5 | Conference, Detroit | Talk + (typically) live demo of the system |2728As of 2026-07-08 the live obligations are the camera-ready chain for accepted papers29and the adjunct tracks (Demos, Posters — deadlines 待核实, read the CFP) for everyone30else; new submissions target the 2027 cycle.3132## Backwards plan for a systems paper3334Work in reverse from the paper deadline; the ordering below is where UIST projects35actually fail, not a generic writing schedule:36371. **T minus 0-1 weeks — submission mechanics.** PCS uploads, anonymity sweeps,38 abstract-field consistency (see `uist-submission`).392. **T minus 1-3 weeks — video figure production.** Scripting, capture, edit,40 captions, anonymization. The video cannot be shot until the system is stable, and41 it competes with the writing for the same people (see `uist-supplementary`).423. **T minus 3-6 weeks — evaluation.** Technical benchmarks and any user study; IRB43 approval must predate this window, so file it in the fall.444. **T minus 6-10 weeks — feature freeze.** Everything demonstrated in the paper45 must exist by here. Features added after freeze belong to the next paper.465. **T minus 10+ weeks — build.** Include one full hardware re-spin or one major47 refactor in the estimate, because there will be one.4849## Owners and risk register5051Assign names, not roles, and write the mitigation before the risk fires:5253```text54RISK OWNER MITIGATION55Hardware breaks in video week <name> Build two units; film B-roll early56Study participants no-show <name> Over-recruit 30%; pilot in freeze week57Video render/caption pipeline <name> Dry-run export at T-3w with dummy edit58Page-limit overflow (10pp body) <name> Appendix plan agreed at T-4w59Rebuttal week hits a holiday <name> Pre-draft objection playbook (uist-author-response)60Camera-ready owner on vacation <name> TAPS + alt-text buddy named at notification61```6263## The two parallel lanes6465UIST is one conference with two archival containers, and a healthy group uses both:6667- **Papers lane** (main proceedings): the full pipeline above.68- **Adjunct lane** (Demos, Posters — separate chairs, separate deadlines, adjunct69 proceedings): a rejected paper's system can still appear at the conference as a70 demo; early-stage work can test community reaction as a poster; the same work must71 not be submitted to both Demos and Posters (the 2026 rule converts it to a demo and72 drops the poster). Decide the fallback lane on notification day, not after the73 adjunct deadlines pass.7475## Planning UIST 2027 from a mid-2026 vantage7677For teams reading this in the live window (post-notification 2026), the next Papers78deadline is roughly nine months out and the calendar is not yet published (待核实 —79watch the 2027 site from its first announcement). Provisional planning rules that80survive cycle drift:8182- Assume the abstract/paper pair lands in **late March ± a few weeks** and the83 conference in the fall; anchor the feature-freeze ten weeks before the assumed84 deadline and adjust when the real dates post.85- Anything involving **human subjects** needs ethics approval filed by roughly86 December; anything involving **custom hardware** needs its final revision ordered87 by January (fab and shipping queues do not respect AoE).88- Book **video-production capacity** — the person, the rig, the edit suite — for89 the two pre-deadline weeks now; it is the least substitutable resource in the90 pipeline.91- Draft the **contribution list before the spring**: if you cannot write three92 capability claims in January, the project is a 2028 paper wearing a 2027 badge.9394## The month-by-month cadence (generic UIST year)9596| Months before deadline | Focus |97|---|---|98| 9-7 | Routing decision, system architecture, ethics filing |99| 7-4 | Core build; related-work sweep running in parallel |100| 4-2.5 | Feature freeze; evaluation harness and pilots |101| 2.5-1 | Studies and technical characterization; paper skeleton |102| 1-0.5 | Video production; full drafts circulating |103| 0.5-0 | Submission mechanics only — nothing new enters the paper |104105## Between cycles106107- File a post-mortem within two weeks of notification while reviews are fresh:108 which review criticism was predictable at freeze time?109- Convert the submission's infrastructure — build scripts, benchmark harnesses,110 capture rigs — into reusable lab property; UIST groups compound or burn out on111 exactly this.112- Watch the next edition's site from its first announcement: dates shift by weeks113 between editions and the length rules have changed across recent cycles.114115## Output format116117```text118[Cycle target] UIST <year> papers / demos / posters / DS119[Today's phase] build / freeze / evaluation / video / submission / review / rebuttal / camera-ready / conference prep120[Critical path] <the single task that moves the finish date>121[Risk register] top three, each with named owner122[Next fixed date] <date + obligation>123```