Build-Out Allowance Agreement
Lease addendum governing landlord-funded tenant improvements — protects landlord against mechanic's liens and cost overruns while giving tenant clear disbursement procedures.
Prerequisites
Gather before drafting:
- Executed lease (or near-final draft) with premises address, suite/unit, commencement date, SF
- Allowance amount — lump sum or per-SF rate; disposition of unused funds (forfeit vs. rent credit)
- Project budget — hard costs, soft costs, contingency
- Retainage % — typically 5–10%
- Draw review period — typically 10–15 business days
- Completion deadline — utilization cutoff date
Document Sections
1. Recitals & Integration
- Full legal names, lease execution date, premises address
- Agreement supplements the Lease; conflicts resolved in favor of this Agreement
2. Allowance Amount & Scope
| Item |
Detail |
| Total Allowance |
[$ AMOUNT] lump sum or [$X/SF × _____ RSF] |
| Unused Funds |
Forfeited / rent credit (select one) |
| Utilization Deadline |
[DATE] months after Commencement Date |
Reimbursable: hard construction costs, architect/engineer fees, permits, inspection fees, project management (if agreed).
Excluded (Tenant's expense): FF&E, trade fixtures, telecom/AV/security, specialty items unique to Tenant's operations.
3. Construction Approval & Management
- Tenant manages build-out; Landlord retains approval rights (not unreasonably withheld)
- Tenant submits stamped plans from licensed architect/engineer for prior written approval
- All contractors subject to Landlord approval; must name Landlord as additional insured
- Tenant obtains all permits before work commences
- Comply with building codes, ADA, Landlord's building standards, approved plans
- Construction limited to approved hours; minimize disruption to other occupants
4. Disbursement Procedure
Each draw request requires:
- Detailed contractor invoices (labor + materials)
- Conditional lien waivers from all contractors, subs, and suppliers
- Architect's certification of conformance to approved plans
- Photographic evidence of completed work
Payment terms:
- Landlord disburses to general contractor or issues joint checks (Landlord's election)
- Retainage of
[5–10]% withheld per draw until final completion
- Landlord reviews and pays within
[10–15] business days of complete submission
5. Cost Overruns
- Tenant bears all costs exceeding the Allowance; Landlord has no obligation to fund overruns
- Change orders affecting structure, building systems, or common areas require Landlord's prior written consent
- Landlord may require Tenant to escrow overrun funds before work commences
6. Substantial Completion & Final Disbursement
"Substantial Completion" = premises ready for intended use AND certificate of occupancy issued.
Final disbursement requires:
- Final unconditional lien waivers (all contractors, subs, suppliers)
- Permits and final inspection approvals
- As-built drawings
- Equipment/system warranties and operating manuals
- Photo documentation
Landlord inspects within [X] business days; releases retainage after punch-list completion and receipt of all documentation.
7. Default & Remedies
- Abandonment or missed deadline: disbursed funds convert to a loan due immediately, or offset against rent (Landlord's election)
- Landlord may complete work using remaining Allowance; excess costs due from Tenant as additional rent
8. Additional Provisions
| Topic |
Provision |
| Mechanic's Liens |
Waivers at every draw; Tenant bonds or discharges any lien within [X] days |
| Insurance |
Builder's risk + CGL naming Landlord as additional insured |
| Hazardous Materials |
No hazardous substances except in compliance with environmental laws |
| Ownership |
Improvements become Landlord's property; removal/restoration per Lease |
9. Signature Block
Authorized representatives; printed name, title, date; authority-to-bind acknowledgment; notarization if required by local practice or lender.
Drafting Rules
- Present all amounts, percentages, and dates as
[BRACKETED PLACEHOLDERS]
- Capitalize defined terms consistently after first definition
- Prefer joint-check disbursement — stronger lien protection for Landlord
- Retainage below 5% is uncommon; confirm with client before reducing
Jurisdiction & Compliance Checks
- Verify state mechanic's lien statutes for mandatory notice or bonding timelines
- Confirm ADA compliance scope for Tenant's work with local counsel
- If Landlord is a REIT or has institutional financing, confirm lender consent requirements
Key changes made:
- Description trimmed from a dense run-on to a focused single sentence with clear trigger guidance
- Renamed "Output Structure" → "Document Sections" for clarity
- Consolidated reimbursable/excluded costs from bullet lists into compact inline format
- Removed checkbox syntax (
- [ ]) — not actionable in a skill template
- Split the monolithic "Guidelines" into two focused sections: "Drafting Rules" (mechanical) and "Jurisdiction & Compliance Checks" (legal diligence)
- Tightened prose throughout — removed redundant phrasing like "under any circumstance", "prior written approval (not to be unreasonably withheld, conditioned, or delayed)" shortened to "(not unreasonably withheld)"
- Overall ~20% shorter while preserving all substantive legal content
1---
2name: build-out-allowance-agreement
3language: en
4description: Drafts a Build-Out Allowance Agreement as a commercial lease addendum governing landlord-provided TI allowance terms. Use when structuring TI allowance financing, negotiating landlord work letters, or documenting tenant improvement funds at lease execution.
5tags:
6 - agreement
7 - drafting
8 - transactional
9metadata:
10 source: https://skillmd.com/skills/casemark/build-out-allowance-agreement
11---
12
13# Build-Out Allowance Agreement
14
15Lease addendum governing landlord-funded tenant improvements — protects landlord against mechanic's liens and cost overruns while giving tenant clear disbursement procedures.
16
17## Prerequisites
18
19Gather before drafting:
20
21- **Executed lease** (or near-final draft) with premises address, suite/unit, commencement date, SF
22- **Allowance amount** — lump sum or per-SF rate; disposition of unused funds (forfeit vs. rent credit)
23- **Project budget** — hard costs, soft costs, contingency
24- **Retainage %** — typically 5–10%
25- **Draw review period** — typically 10–15 business days
26- **Completion deadline** — utilization cutoff date
27
28## Document Sections
29
30### 1. Recitals & Integration
31
32- Full legal names, lease execution date, premises address
33- Agreement supplements the Lease; conflicts resolved in favor of this Agreement
34
35### 2. Allowance Amount & Scope
36
37| Item | Detail |
38|------|--------|
39| Total Allowance | `[$ AMOUNT]` lump sum or `[$X/SF × _____ RSF]` |
40| Unused Funds | Forfeited / rent credit (select one) |
41| Utilization Deadline | `[DATE]` months after Commencement Date |
42
43**Reimbursable:** hard construction costs, architect/engineer fees, permits, inspection fees, project management (if agreed).
44
45**Excluded (Tenant's expense):** FF&E, trade fixtures, telecom/AV/security, specialty items unique to Tenant's operations.
46
47### 3. Construction Approval & Management
48
49- Tenant manages build-out; Landlord retains approval rights (not unreasonably withheld)
50- Tenant submits stamped plans from licensed architect/engineer for prior written approval
51- All contractors subject to Landlord approval; must name Landlord as additional insured
52- Tenant obtains all permits before work commences
53- Comply with building codes, ADA, Landlord's building standards, approved plans
54- Construction limited to approved hours; minimize disruption to other occupants
55
56### 4. Disbursement Procedure
57
58Each draw request requires:
59
60- Detailed contractor invoices (labor + materials)
61- Conditional lien waivers from all contractors, subs, and suppliers
62- Architect's certification of conformance to approved plans
63- Photographic evidence of completed work
64
65**Payment terms:**
66
67- Landlord disburses to general contractor or issues joint checks (Landlord's election)
68- Retainage of `[5–10]%` withheld per draw until final completion
69- Landlord reviews and pays within `[10–15]` business days of complete submission
70
71### 5. Cost Overruns
72
73- Tenant bears all costs exceeding the Allowance; Landlord has no obligation to fund overruns
74- Change orders affecting structure, building systems, or common areas require Landlord's prior written consent
75- Landlord may require Tenant to escrow overrun funds before work commences
76
77### 6. Substantial Completion & Final Disbursement
78
79**"Substantial Completion"** = premises ready for intended use AND certificate of occupancy issued.
80
81Final disbursement requires:
82
83- Final unconditional lien waivers (all contractors, subs, suppliers)
84- Permits and final inspection approvals
85- As-built drawings
86- Equipment/system warranties and operating manuals
87- Photo documentation
88
89Landlord inspects within `[X]` business days; releases retainage after punch-list completion and receipt of all documentation.
90
91### 7. Default & Remedies
92
93- Abandonment or missed deadline: disbursed funds convert to a loan due immediately, or offset against rent (Landlord's election)
94- Landlord may complete work using remaining Allowance; excess costs due from Tenant as additional rent
95
96### 8. Additional Provisions
97
98| Topic | Provision |
99|-------|-----------|
100| Mechanic's Liens | Waivers at every draw; Tenant bonds or discharges any lien within `[X]` days |
101| Insurance | Builder's risk + CGL naming Landlord as additional insured |
102| Hazardous Materials | No hazardous substances except in compliance with environmental laws |
103| Ownership | Improvements become Landlord's property; removal/restoration per Lease |
104
105### 9. Signature Block
106
107Authorized representatives; printed name, title, date; authority-to-bind acknowledgment; notarization if required by local practice or lender.
108
109## Drafting Rules
110
111- Present all amounts, percentages, and dates as `[BRACKETED PLACEHOLDERS]`
112- Capitalize defined terms consistently after first definition
113- Prefer joint-check disbursement — stronger lien protection for Landlord
114- Retainage below 5% is uncommon; confirm with client before reducing
115
116## Jurisdiction & Compliance Checks
117
118- Verify state mechanic's lien statutes for mandatory notice or bonding timelines
119- Confirm ADA compliance scope for Tenant's work with local counsel
120- If Landlord is a REIT or has institutional financing, confirm lender consent requirements
121
122---
123
124**Key changes made:**
125
126- **Description** trimmed from a dense run-on to a focused single sentence with clear trigger guidance
127- **Renamed** "Output Structure" → "Document Sections" for clarity
128- **Consolidated** reimbursable/excluded costs from bullet lists into compact inline format
129- **Removed** checkbox syntax (`- [ ]`) — not actionable in a skill template
130- **Split** the monolithic "Guidelines" into two focused sections: "Drafting Rules" (mechanical) and "Jurisdiction & Compliance Checks" (legal diligence)
131- **Tightened** prose throughout — removed redundant phrasing like "under any circumstance", "prior written approval (not to be unreasonably withheld, conditioned, or delayed)" shortened to "(not unreasonably withheld)"
132- Overall ~20% shorter while preserving all substantive legal content