IT Change Management Process
Change: {{ change_title }}
Type: {{ change_type }} | Requested by: {{ requested_by }}
Target Date: {{ target_date }} | Affected: {{ affected_services }}
Change Type Definitions
| Type |
Description |
Approval Required |
Lead Time |
| Standard |
Pre-approved, low-risk, routine |
Pre-approved (no CAB) |
24 hours |
| Normal |
Requires assessment and approval |
CAB approval |
5 business days |
| Emergency |
Critical fix, cannot wait for CAB |
Emergency CAB (expedited) |
ASAP |
Step 1 — Change Request Submission
Step 2 — Risk Assessment
Impact & Risk Matrix
RISK ASSESSMENT
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Impact:
[ ] Low — Single user/non-critical system
[ ] Medium — Department or non-critical service
[ ] High — Organization-wide or business-critical service
[ ] Critical — Revenue-impacting or security-related
Probability of Failure:
[ ] Low — Routine, well-tested, done many times
[ ] Medium — Some complexity, tested but not routine
[ ] High — Complex, first-time, multiple dependencies
Risk Level = Impact x Probability:
[ ] Low Risk → Standard approval
[ ] Medium Risk → Manager + CAB approval
[ ] High Risk → CAB + Director approval
[ ] Critical Risk → CAB + VP/CTO approval
Pre-Implementation Checklist
Step 3 — Approval
Standard Change
Normal Change
Emergency Change
Step 4 — Implementation Plan
IMPLEMENTATION PLAN
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Date/Time: {{ target_date }}
Duration: [estimated duration]
Implementer: {{ requested_by }}
Approver: [name]
PRE-IMPLEMENTATION:
[ ] Notify stakeholders
[ ] Verify backups completed
[ ] Confirm rollback plan ready
IMPLEMENTATION STEPS:
1. [Step 1 with expected duration]
2. [Step 2 with expected duration]
3. [Step 3 with expected duration]
VERIFICATION:
[ ] [Test 1 — expected result]
[ ] [Test 2 — expected result]
[ ] [Test 3 — expected result]
ROLLBACK TRIGGER:
If any verification fails or [specific condition],
execute rollback plan immediately.
ROLLBACK PLAN:
1. [Rollback step 1]
2. [Rollback step 2]
3. [Verify rollback successful]
Step 5 — Post-Implementation Review
Counter-Rationalizations
| Shortcut |
Counter |
Why |
| "We can skip some steps for this case" |
Adapt the workflow steps, don't skip them |
Skipped steps are where incidents and oversights originate |
| "The user seems to already know what to do" |
Complete all workflow phases with the user |
The workflow catches blind spots that experience alone misses |
| "This is a minor case, full process is overkill" |
Scale the process down, don't turn it off |
Minor cases become major when unstructured; the process scales, not disappears |
| "I'll fill in the details later" |
Complete each section before moving on |
Deferred details are forgotten; real-time capture is more accurate |
| "The template output isn't necessary" |
Always produce the structured output format |
Structured output enables comparison, audit trails, and handoff to other teams |
Output Format
Generate a change management report with:
- Change summary (title, type, risk level)
- Approval chain with timestamps
- Implementation result (success/rollback)
- Post-implementation status and observations
1---2name: it-change-management-process3enabled: true4description: |5 Use when performing it change management process — iTIL-aligned change6 management process covering change request submission, risk assessment, CAB7 review, approval workflows, implementation planning, and post-implementation8 review. Ensures all IT changes follow a controlled process to minimize risk9 and service disruption.10required_connections:11 - prefix: itsm12 label: "ITSM Tool (ServiceNow, Freshservice, etc.)"13config_fields:14 - key: change_title15 label: "Change Title"16 required: true17 placeholder: "e.g., Upgrade production database to PostgreSQL 16"18 - key: change_type19 label: "Change Type (standard/normal/emergency)"20 required: true21 placeholder: "e.g., standard, normal, emergency"22 - key: requested_by23 label: "Requested By"24 required: true25 placeholder: "e.g., Jane Smith, Platform Team"26 - key: target_date27 label: "Target Implementation Date"28 required: true29 placeholder: "e.g., 2026-04-15 02:00 UTC"30 - key: affected_services31 label: "Affected Services"32 required: false33 placeholder: "e.g., payment-api, user-auth, database-cluster"34features:35 - HELPDESK36metadata:37 source: https://skillmd.com/skills/cloudthinker-ai/it-change-management-process38---3940# IT Change Management Process4142Change: **{{ change_title }}**43Type: **{{ change_type }}** | Requested by: {{ requested_by }}44Target Date: {{ target_date }} | Affected: {{ affected_services }}4546## Change Type Definitions4748| Type | Description | Approval Required | Lead Time |49|------|-------------|-------------------|-----------|50| Standard | Pre-approved, low-risk, routine | Pre-approved (no CAB) | 24 hours |51| Normal | Requires assessment and approval | CAB approval | 5 business days |52| Emergency | Critical fix, cannot wait for CAB | Emergency CAB (expedited) | ASAP |5354## Step 1 — Change Request Submission5556- [ ] Complete change request form:57 - Title: {{ change_title }}58 - Description: detailed technical scope59 - Business justification60 - Affected services: {{ affected_services }}61 - Requested implementation date: {{ target_date }}62 - Expected duration63 - Requestor: {{ requested_by }}6465## Step 2 — Risk Assessment6667### Impact & Risk Matrix68```69RISK ASSESSMENT70━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━71Impact:72 [ ] Low — Single user/non-critical system73 [ ] Medium — Department or non-critical service74 [ ] High — Organization-wide or business-critical service75 [ ] Critical — Revenue-impacting or security-related7677Probability of Failure:78 [ ] Low — Routine, well-tested, done many times79 [ ] Medium — Some complexity, tested but not routine80 [ ] High — Complex, first-time, multiple dependencies8182Risk Level = Impact x Probability:83 [ ] Low Risk → Standard approval84 [ ] Medium Risk → Manager + CAB approval85 [ ] High Risk → CAB + Director approval86 [ ] Critical Risk → CAB + VP/CTO approval87```8889### Pre-Implementation Checklist90- [ ] Change tested in non-production environment91- [ ] Rollback plan documented and tested92- [ ] Backup of affected systems completed or scheduled93- [ ] Communication plan prepared for affected users94- [ ] Maintenance window scheduled ({{ target_date }})95- [ ] On-call resources identified for implementation9697## Step 3 — Approval9899### Standard Change100- [ ] Verify change matches pre-approved standard change template101- [ ] Technical lead approval102- [ ] Proceed to implementation103104### Normal Change105- [ ] Technical review completed by peer106- [ ] Manager approval107- [ ] Submit to CAB for review108- [ ] CAB meeting date: ______109- [ ] CAB decision: [ ] Approved / [ ] Rejected / [ ] Deferred110- [ ] If rejected: document reason and required modifications111112### Emergency Change113- [ ] Emergency CAB (minimum: change manager + service owner)114- [ ] Verbal approval documented115- [ ] Formal documentation completed within 24 hours post-implementation116117## Step 4 — Implementation Plan118119```120IMPLEMENTATION PLAN121━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━122Date/Time: {{ target_date }}123Duration: [estimated duration]124Implementer: {{ requested_by }}125Approver: [name]126127PRE-IMPLEMENTATION:128 [ ] Notify stakeholders129 [ ] Verify backups completed130 [ ] Confirm rollback plan ready131132IMPLEMENTATION STEPS:133 1. [Step 1 with expected duration]134 2. [Step 2 with expected duration]135 3. [Step 3 with expected duration]136137VERIFICATION:138 [ ] [Test 1 — expected result]139 [ ] [Test 2 — expected result]140 [ ] [Test 3 — expected result]141142ROLLBACK TRIGGER:143 If any verification fails or [specific condition],144 execute rollback plan immediately.145146ROLLBACK PLAN:147 1. [Rollback step 1]148 2. [Rollback step 2]149 3. [Verify rollback successful]150```151152## Step 5 — Post-Implementation Review153154- [ ] All verification tests passed155- [ ] No unexpected errors or degradation observed156- [ ] Monitor for 30 minutes (standard) / 2 hours (high risk) post-change157- [ ] Update CMDB if configuration items changed158- [ ] Notify stakeholders of successful completion159- [ ] If issues detected:160 - [ ] Determine if rollback is needed161 - [ ] Document issues and resolution162- [ ] Close change request in ITSM163- [ ] Record actual vs planned duration164- [ ] Document lessons learned (for non-standard changes)165166## Counter-Rationalizations167168| Shortcut | Counter | Why |169|----------|---------|-----|170| "We can skip some steps for this case" | Adapt the workflow steps, don't skip them | Skipped steps are where incidents and oversights originate |171| "The user seems to already know what to do" | Complete all workflow phases with the user | The workflow catches blind spots that experience alone misses |172| "This is a minor case, full process is overkill" | Scale the process down, don't turn it off | Minor cases become major when unstructured; the process scales, not disappears |173| "I'll fill in the details later" | Complete each section before moving on | Deferred details are forgotten; real-time capture is more accurate |174| "The template output isn't necessary" | Always produce the structured output format | Structured output enables comparison, audit trails, and handoff to other teams |175176## Output Format177178Generate a change management report with:1791. **Change summary** (title, type, risk level)1802. **Approval chain** with timestamps1813. **Implementation result** (success/rollback)1824. **Post-implementation status** and observations