Commercial Claim Quantification
Overview
Quantify commercial claims by identifying contractual entitlement clauses, calculating time and cost impacts, gathering supporting evidence, and compiling claim submissions.
Announce at start: "I'm using the commercial-claim-quantification skill to quantify a commercial claim."
When to Use This Skill
Trigger Conditions:
- Contract variation or change event occurs
- Employer-caused delay experienced
- Additional work performed beyond scope
- Force majeure event triggers entitlement
Prerequisites:
- Event that triggers entitlement identified
- Contract reviewed for relevant clauses
- Records of the event maintained
Step-by-Step Procedure
Step 1: Identify Claim Entitlement
- Identify the contractual clause providing entitlement
- Verify the clause applies to the current event
- Check notice requirements and compliance
- Document the entitlement basis
Step 2: Quantify Time Impact
- Identify planned completion date vs. delayed date
- Determine if event is on critical path
- Calculate days of Extension of Time (EOT)
- Document the delay analysis method used
Step 3: Quantify Cost Impact
- Direct Costs: Additional labor, materials, equipment directly caused by the event
- Indirect Costs: Site overhead, administration, extended preliminaries during delay period
- Overheads: Head office overheads calculated using standard formula
- Profit: Reasonable profit on the claim if permissible under contract
Step 4: Gather Supporting Evidence
- Contemporary records (daily logs, correspondence, meeting minutes)
- Cost records (timesheets, invoices, payment records)
- Schedule records (baseline schedule, updated schedules)
- Photographs and site inspection records
Step 5: Compile Claim Submission
- Executive summary of the claim
- Entitlement basis (which clause, why it applies)
- Time claim (EOT calculation)
- Cost claim (detailed breakdown)
- Supporting evidence index
- Conclusion and relief sought
Success Criteria
- Contractual entitlement clause identified
- Time impact quantified with EOT days calculated
- Cost impact calculated (direct, indirect, overhead, profit)
- Supporting evidence compiled and indexed
- Claim submission document produced with all elements
Common Pitfalls
- Missing Notice Requirements — Many contracts require notice within a specific period. Missing this can bar the claim.
- Inadequate Evidence — Claims without contemporary records are difficult to substantiate. Maintain records from day one.