Permit to Work Management
Overview
End-to-end management of permit-to-work (PTW) processes for high-risk activities including hot work, confined space, working at height, electrical isolation, excavation, and lifting operations. Primary agent: HSE Safety Manager.
Triggers
- Work activity requiring permit identified
- Work method change requiring different permit type
- Permit extension request
- Emergency work requiring expedited permit
- Permit suspension or cancellation
Prerequisites
- Work scope and location identified
- Risk assessment completed for the activity
- Qualified personnel available for the work
- Required safety equipment identified and available
- Authorization hierarchy defined
Steps
Step 1: Permit Type Classification
Classify permit type based on work activity:
- Hot Work Permit → Welding, cutting, grinding, open flame
- Confined Space Permit → Entry into tanks, vessels, pits, enclosed spaces
- Working at Height Permit → Work above 1.8m without edge protection
- Electrical Isolation Permit → Work on energized systems or isolation verification
- Excavation Permit → Ground excavation, trenching, underground work
- Lifting Permit → Critical lifts (over 75% crane capacity, tandem lifts)
Step 2: Hazard Identification
Identify all hazards associated with the permitted activity:
- Review work location and surroundings
- Check adjacent activities that may conflict
- Identify environmental hazards (weather, atmospheric conditions)
- Identify equipment and material hazards
Step 3: Control Measures
Define required control measures for each hazard:
- Specify personal protective equipment (PPE)
- Define isolation requirements (LOTO, gas testing, barricades)
- Specify atmospheric monitoring requirements
- Define emergency response arrangements
- Specify supervision and monitoring requirements
Step 4: Authorization Workflow
Route permit through authorization chain:
- Submit → Issuer submits permit application
- Review → Safety reviewer checks completeness
- Approve → Authorizing person approves permit
- Accept → Performing team accepts permit
- Monitor → Continuous monitoring during work
- Close → Work complete, site cleared, permit closed
Step 5: Permit Execution & Monitoring
- Verify all control measures are in place before work starts
- Monitor conditions continuously during work
- Conduct periodic checks per permit requirements
- Document any permit suspensions or condition changes
- Ensure permit displayed at work location
Step 6: Permit Closure
- Verify work complete and site cleared
- Remove all temporary safety measures
- Confirm no outstanding hazards
- Record lessons learned and observations
- Archive permit record
Success Criteria
- Correct permit type identified and applied
- All hazards identified with appropriate controls
- Authorization chain completed before work starts
- Permit displayed and conditions monitored
- Permit properly closed and archived
Common Pitfalls
- Wrong permit type → Incorrect classification leads to inadequate controls
- Missing adjacent hazards → Check surrounding activities before approval
- Expired permits → Track permit expiry and extension requests
- Incomplete closures → Ensure all closure steps are verified
Cross-References
safety/hazard-identification/SKILL.md— Hazard identification sourcesafety/inspection-workflow/SKILL.md— Permit inspection during execution