Launch Calendar
Generates the complete launch calendar, master burn-down seed list, and meeting schedule
for an Every L/XL launch, working back from the launch date per the canonical process.
This is the date engine of the Launch Architecture Skillset: it computes; the
notion-launch-scaffold skill places.
v1.1. Supersedes the local v1 skill, which drifted from the ruled process (it had Dan
at two gates; the canon rules three). Generate from launches/canonical-process.md only.
When to invoke
- "Build a launch calendar," "plan the launch of X," "work back from [date]"
- "When does the brand work need to start," "map out the launch timeline"
- "What dates do the calls go on"
- Any request to schedule launch work, meetings, or gates for an L/XL launch
Rules of computation
- Real date arithmetic, always a script, never mental math. Week 8 Monday anchors the work-back; Week k Monday = Week 8 Monday − (8 − k) × 7 days. Naming weeks precede Week 1 (canon Rule 5).
- The collision rule (ruled Jul 4 2026). Monday or Tuesday launch → the all-hands window becomes the five business days ending on launch day; the pricing hard lock moves to that window's first Monday. Apply without flags.
- A soft launch date makes every artifact DRAFT. The date is confirmed only by the product owner with feature freeze; label everything accordingly and re-baseline on confirmation. Re-baselining regenerates dates; it never compresses gates away.
- Mid-flight (L) entry: start the work-back at the first incomplete phase. If the remaining runway can't hold the remaining phases, lead with that — a short true "this date doesn't fit" beats a complete-looking calendar with hidden zero-slack. When slack is zero, state the consequence on the calendar itself.
- Gates land on Fridays of their gate week, labeled (proposed) until scheduled. Dan's three holds (brief, final web design, Launch Week) are placed in Week 1 — in person when possible.
Outputs
- Dates table — every phase, gate, and lock with its computed date and approver roster per the canon (Douglas at every gate; Brandon + product GM co-rule; Dan ×3; Austin ×2).
- Meeting schedule — the canon's meeting set instantiated with real dates: kickoff, weekly standups (Weeks 1–4), twice-weekly (5–7), daily all-hands (the Week 8 window), the four approval meetings, retro.
- Burn-down seeds — the phase checklists as task rows (deliverable, owner, deadline,
note) ready for
notion-launch-scaffoldto place.
Dependencies
foundation/marketing-oslaunches/canonical-process.md(loaded always — spine, rules, meeting set, rosters)
Quick checklist
- Launch date confirmation status established first; DRAFT labels if soft
- Dates computed by script; collision rule applied for Mon/Tue launches
- Mid-flight: completed phases marked, work-back starts at first incomplete phase
- Slack shown honestly; zero-slack named on the calendar
- Dan's three holds placed; approver rosters per canon on every gate
- Dates table + meeting schedule + burn-down seeds delivered together