Design Verification Plan and Report (DVP&R)
When to use
Use this skill when:
- Creating a DVP for a new part design during APQP Phase 2
- Reviewing a supplier's DVP for completeness and DFMEA alignment
- Determining which tests are required for a specific failure mode or design characteristic
- Tracking test completion and recording results (the "R" in DVP&R)
- Assessing whether a design change requires additional validation testing
Prerequisites
- DFMEA with all failure modes identified and AP ratings assigned
- Engineering drawing with all characteristics defined
- Customer design specifications and performance requirements
- List of applicable standards and test methods (customer spec, ISO, SAE, etc.)
Workflow
Step 1 — Understand the DVP structure
The DVP&R is a table with one row per test. Each test must address at least one failure mode or design characteristic from the DFMEA.
The linkage rule: Every H-AP (High Action Priority) failure mode in the DFMEA must have at least one corresponding test in the DVP. If a failure mode has no test, document why (e.g., analysis-only justification with sign-off).
Step 2 — Build each DVP row
| Column |
What to enter |
| Test number |
Sequential reference (e.g., DVP-001) |
| DFMEA reference |
Failure mode number(s) this test addresses |
| Test name / description |
Specific name of the test (not "durability test" — use "salt spray 240h per ASTM B117") |
| Test specification |
Standard or specification number with version (e.g., ASTM B117-19, SAE J2530, customer spec DS-XYZ) |
| Pass/fail criteria |
Exact acceptance criteria (e.g., "no rust after 240h", "burst pressure > 150 bar", "dimension within ±0.05 mm") |
| Sample size |
Number of parts to test |
| Who performs |
Internal lab, external accredited lab, customer lab |
| Phase |
P = Prototype, PL = Pre-launch, PR = Production |
| Planned date |
Date test is scheduled to complete |
| Actual date |
Date test was completed |
| Result |
Pass / Fail / In progress |
| Report reference |
Lab report number or document reference |
| Comments |
Failures, deviations, re-test requirements |
Step 3 — Determine required tests
For each DFMEA failure mode, identify the test category:
Functional / performance tests:
- Tests that verify the product performs its intended function
- Examples: burst pressure, tensile strength, electrical resistance, flow rate
- Must demonstrate the product meets its design intent specifications
Environmental / durability tests:
- Tests that simulate the product's operating environment over its design life
- Examples: thermal cycling, salt spray, vibration, UV exposure, humidity
- Duration and cycles must represent the design life or accelerated equivalent
Safety / regulatory tests:
- Tests required by law, regulation, or homologation
- Examples: ECE R10 (EMC), FMVSS standards, ECE R94/R95 (crash), REACH, RoHS
- Must be performed by accredited lab; results must accompany PPAP
Dimensional / material tests:
- Verification that design dimensions and material properties are achieved
- Examples: 3D scan, CMM, tensile test, hardness test, chemical composition
- Must reference the specific drawing characteristic or material specification
Reliability / life tests:
- Tests that verify the product meets its reliability target (e.g., B10 life)
- Examples: fatigue testing, accelerated aging, wear testing
- Test plan must include correlation between accelerated test and field life
Step 4 — Populate timing per APQP phase
| Phase |
Tests due |
| Prototype (P) |
Tests on design concept — functional, dimensional, preliminary environmental |
| Pre-launch (PL) |
Tests on tooled parts — full environmental, durability, all safety/regulatory |
| Production (PR) |
Confirmation tests on production parts — dimensional, safety, any tests with production-specific requirements |
Not all tests need to run in all phases. Focus safety and regulatory tests on Pre-launch or Production parts.
Step 5 — Track completion (the "R" in DVP&R)
Update the DVP after each test:
- Record actual completion date
- Record Pass/Fail result
- For any Fail: log a DFMEA action (or open an 8D if failure escapes to customer)
- Re-test after corrective action — reference the re-test as a new row with the original DVP number + suffix (e.g., DVP-012-R1)
At PPAP submission: all DVP tests must show "Pass" or have a documented customer-approved deviation. If a test is still in progress at PPAP submission (e.g., a long-duration life test), a formal customer deviation request must be submitted with: the test in progress, the expected completion date, the interim risk assessment, and the customer's written acceptance. The PPAP approval will be conditional until the test completes with a Pass result.
Engineering changes: If the DFMEA is updated during the design phase and adds new H-AP failure modes, the DVP must be updated to cover them before the next gate review. A DVP revision that is behind the current DFMEA revision is a gap — the DVP&R revision must match or exceed the DFMEA revision at PPAP submission.
Step 6 — Audit an existing DVP
When reviewing a supplier's or internal DVP, check:
Validation criteria
A complete DVP&R for PPAP submission must:
- Reference every H-AP failure mode from the DFMEA
- Have specific, standard-referenced test methods (not "per engineering judgement")
- Show Pass results for all tests (or customer-approved deviations)
- Have accredited lab reports for all safety/regulatory tests
- Be signed off by design engineering and quality
Common mistakes
- DVP created with generic tests not linked to specific DFMEA failure modes
- Pass/fail criteria defined as "meets spec" without stating what the spec is
- All tests assigned to internal lab when regulatory tests require external accreditation
- DVP not updated when DFMEA adds new H-AP failure modes during design reviews
- Re-tests after failures not documented — original Fail result erased
- Sample size of 1 for durability or life tests (statistically meaningless)
- DVP not updated to "Report" status at PPAP — submitted as plan, not results
Output Format
At the start of each use, ask the user:
"How would you like to receive the output?
A — Structured Markdown (formatted tables and sections, ready to copy)
B — Plain tables (simplified structure for Excel or Word)
C — Narrative report (flowing text for a formal document or email)
Default: A."
Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.
Changelog
| Version |
Date |
Author |
Change |
| 1.0 |
2026-06-06 |
@RBraga01 |
Initial release |
| 1.1 |
2026-06-06 |
@migmcc |
Added guidance for tests in-progress at PPAP submission (customer deviation process); added DVP revision synchronisation with DFMEA requirement |
1---2name: dvp-test-plan3description: >-4 Design Verification Plan and Report (DVP&R) — build or review a test plan that links each DFMEA5 failure mode to a specific test, pass/fail criterion, sample size, and timing. Use when creating6 a DVP for a new design, reviewing a supplier's DVP for completeness, or auditing whether all7 design risks are covered by validation testing. Covers IATF 16949 §8.3.4.3 and AIAG APQP Phase 2.8license: MIT9metadata:10 author: RBraga0111 version: "1.1"12 iso-9001: "8.3.4"13 iatf-16949: "8.3.4.3"14 domain: quality-engineering15 subdomain: planning16 industries: automotive,electronics,aerospace,medical,general17 status: approved18 created: "2026-06-06"19 last_updated: "2026-06-06"20 updated_by: migmcc21 reviewed_by: RBraga0122 standard_edition: "IATF 16949:2016 §8.3.4.3 / AIAG APQP 2nd Edition"23---2425# Design Verification Plan and Report (DVP&R)2627## When to use2829Use this skill when:30- Creating a DVP for a new part design during APQP Phase 231- Reviewing a supplier's DVP for completeness and DFMEA alignment32- Determining which tests are required for a specific failure mode or design characteristic33- Tracking test completion and recording results (the "R" in DVP&R)34- Assessing whether a design change requires additional validation testing3536## Prerequisites3738- DFMEA with all failure modes identified and AP ratings assigned39- Engineering drawing with all characteristics defined40- Customer design specifications and performance requirements41- List of applicable standards and test methods (customer spec, ISO, SAE, etc.)4243## Workflow4445### Step 1 — Understand the DVP structure4647The DVP&R is a table with one row per test. Each test must address at least one failure mode or design characteristic from the DFMEA.4849**The linkage rule:** Every H-AP (High Action Priority) failure mode in the DFMEA must have at least one corresponding test in the DVP. If a failure mode has no test, document why (e.g., analysis-only justification with sign-off).5051### Step 2 — Build each DVP row5253| Column | What to enter |54|--------|--------------|55| Test number | Sequential reference (e.g., DVP-001) |56| DFMEA reference | Failure mode number(s) this test addresses |57| Test name / description | Specific name of the test (not "durability test" — use "salt spray 240h per ASTM B117") |58| Test specification | Standard or specification number with version (e.g., ASTM B117-19, SAE J2530, customer spec DS-XYZ) |59| Pass/fail criteria | Exact acceptance criteria (e.g., "no rust after 240h", "burst pressure > 150 bar", "dimension within ±0.05 mm") |60| Sample size | Number of parts to test |61| Who performs | Internal lab, external accredited lab, customer lab |62| Phase | P = Prototype, PL = Pre-launch, PR = Production |63| Planned date | Date test is scheduled to complete |64| Actual date | Date test was completed |65| Result | Pass / Fail / In progress |66| Report reference | Lab report number or document reference |67| Comments | Failures, deviations, re-test requirements |6869### Step 3 — Determine required tests7071For each DFMEA failure mode, identify the test category:7273**Functional / performance tests:**74- Tests that verify the product performs its intended function75- Examples: burst pressure, tensile strength, electrical resistance, flow rate76- Must demonstrate the product meets its design intent specifications7778**Environmental / durability tests:**79- Tests that simulate the product's operating environment over its design life80- Examples: thermal cycling, salt spray, vibration, UV exposure, humidity81- Duration and cycles must represent the design life or accelerated equivalent8283**Safety / regulatory tests:**84- Tests required by law, regulation, or homologation85- Examples: ECE R10 (EMC), FMVSS standards, ECE R94/R95 (crash), REACH, RoHS86- Must be performed by accredited lab; results must accompany PPAP8788**Dimensional / material tests:**89- Verification that design dimensions and material properties are achieved90- Examples: 3D scan, CMM, tensile test, hardness test, chemical composition91- Must reference the specific drawing characteristic or material specification9293**Reliability / life tests:**94- Tests that verify the product meets its reliability target (e.g., B10 life)95- Examples: fatigue testing, accelerated aging, wear testing96- Test plan must include correlation between accelerated test and field life9798### Step 4 — Populate timing per APQP phase99100| Phase | Tests due |101|-------|-----------|102| Prototype (P) | Tests on design concept — functional, dimensional, preliminary environmental |103| Pre-launch (PL) | Tests on tooled parts — full environmental, durability, all safety/regulatory |104| Production (PR) | Confirmation tests on production parts — dimensional, safety, any tests with production-specific requirements |105106Not all tests need to run in all phases. Focus safety and regulatory tests on Pre-launch or Production parts.107108### Step 5 — Track completion (the "R" in DVP&R)109110Update the DVP after each test:111- Record actual completion date112- Record Pass/Fail result113- For any Fail: log a DFMEA action (or open an 8D if failure escapes to customer)114- Re-test after corrective action — reference the re-test as a new row with the original DVP number + suffix (e.g., DVP-012-R1)115116At PPAP submission: all DVP tests must show "Pass" or have a documented customer-approved deviation. If a test is still in progress at PPAP submission (e.g., a long-duration life test), a formal customer deviation request must be submitted with: the test in progress, the expected completion date, the interim risk assessment, and the customer's written acceptance. The PPAP approval will be conditional until the test completes with a Pass result.117118**Engineering changes:** If the DFMEA is updated during the design phase and adds new H-AP failure modes, the DVP must be updated to cover them before the next gate review. A DVP revision that is behind the current DFMEA revision is a gap — the DVP&R revision must match or exceed the DFMEA revision at PPAP submission.119120### Step 6 — Audit an existing DVP121122When reviewing a supplier's or internal DVP, check:123124- [ ] Every H-AP DFMEA failure mode has at least one corresponding test125- [ ] Test specifications reference a specific standard or document (not "internal test")126- [ ] Pass/fail criteria are objective and measurable (not "acceptable appearance")127- [ ] Sample sizes are adequate (not "1 sample" for durability/life tests)128- [ ] Safety and regulatory tests are assigned to an accredited external lab129- [ ] All results show "Pass" (or documented deviations with customer approval)130- [ ] Failed tests have a corresponding DFMEA update or corrective action reference131- [ ] DVP revision is aligned with the current DFMEA revision132133## Validation criteria134135A complete DVP&R for PPAP submission must:136- Reference every H-AP failure mode from the DFMEA137- Have specific, standard-referenced test methods (not "per engineering judgement")138- Show Pass results for all tests (or customer-approved deviations)139- Have accredited lab reports for all safety/regulatory tests140- Be signed off by design engineering and quality141142## Common mistakes143144- DVP created with generic tests not linked to specific DFMEA failure modes145- Pass/fail criteria defined as "meets spec" without stating what the spec is146- All tests assigned to internal lab when regulatory tests require external accreditation147- DVP not updated when DFMEA adds new H-AP failure modes during design reviews148- Re-tests after failures not documented — original Fail result erased149- Sample size of 1 for durability or life tests (statistically meaningless)150- DVP not updated to "Report" status at PPAP — submitted as plan, not results151152## Output Format153154At the start of each use, ask the user:155156> "How would you like to receive the output?157> **A** — Structured Markdown (formatted tables and sections, ready to copy)158> **B** — Plain tables (simplified structure for Excel or Word)159> **C** — Narrative report (flowing text for a formal document or email)160>161> Default: A."162163Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.164165## Changelog166167| Version | Date | Author | Change |168|---------|------|--------|--------|169| 1.0 | 2026-06-06 | @RBraga01 | Initial release |170| 1.1 | 2026-06-06 | @migmcc | Added guidance for tests in-progress at PPAP submission (customer deviation process); added DVP revision synchronisation with DFMEA requirement |