Managing Construction Lending
When To Use
- Underwriting or monitoring a construction loan (ground-up, renovation, or adaptive reuse)
- Reviewing a draw request for approval or flagging budget variances
- Assessing completion risk mid-project (schedule delays, cost overruns, contractor issues)
- Preparing a construction loan status report for credit committee, REIT portfolio review, or investor reporting
- Evaluating a construction-to-permanent loan conversion readiness
Inputs To Gather
- Loan documents: commitment letter, construction loan agreement, guaranty, interest reserve terms
- Project budget: hard costs, soft costs, contingency, developer fee, interest reserve line items
- Draw schedule: original schedule of values (SOV), all prior draw requests with inspector reports
- Current draw request: AIA G702/G703 or equivalent, lien waivers (conditional and unconditional), stored materials documentation
- Title update: date-down endorsement or bring-down confirming no intervening liens
- Inspection report: third-party inspector's percent-complete assessment per line item
- Permits and approvals: building permit status, TCO/CO timeline, zoning compliance [VERIFY jurisdiction-specific requirements]
- Contractor information: general contractor financials, bonding (if applicable), subcontractor list
- Insurance certificates: builder's risk, GL, workers' comp — confirm coverage amounts and expiration dates
- Market data (if relevant): comparable rents/sales, absorption rates for the project type and submarket
Workflow
Validate loan structure and terms
- Confirm loan amount, LTC ratio, maturity date, extension options, and interest rate (fixed/floating, spread, floor)
- Identify recourse vs. non-recourse structure and guarantor obligations (completion, carry, bad-boy carve-outs)
- Note holdback provisions, retainage percentage, and any earn-out or performance-based release conditions
- Flag any unfunded commitments, future-advance mechanics, or interest reserve burn-rate concerns
Analyze the project budget
- Compare original approved budget to current budget; identify any reallocations or change orders
- Calculate hard-cost and soft-cost contingency remaining as a percentage of total budget
- Assess developer fee structure (deferred vs. drawn pro rata) and impact on cash flow
- Flag line items where costs-to-date plus costs-to-complete exceed the budgeted amount
Process the draw request
- Match each line item on the draw request against the SOV and inspector's percent-complete
- Confirm retainage is withheld at the contractual rate (typically 5–10%) [VERIFY per loan agreement]
- Verify lien waivers are current: unconditional for prior draws, conditional for the current draw
- Check stored materials documentation (insurance, warehouse receipts, title transfer)
- Reconcile the draw amount against the remaining loan balance and confirm the loan is not over-advanced
Assess completion risk
- Compare actual percent-complete to scheduled percent-complete; quantify any time variance
- Evaluate remaining contingency relative to project stage (contingency should not be exhausted before 75% completion)
- Review contractor performance: change-order frequency, subcontractor turnover, quality issues noted in inspection reports
- Identify external risks: permit delays, utility hookup timelines, weather-sensitive work remaining, supply-chain issues
- Determine whether remaining loan proceeds (including contingency and interest reserve) are sufficient to fund project completion
Prepare the status report
- Summarize loan-level metrics: outstanding balance, percent funded, remaining availability, weighted-average cost of funds
- Present budget variance analysis (original vs. current vs. projected at completion)
- Include a draw history table: draw number, date, amount requested, amount approved, cumulative funded
- State completion timeline with key milestones (structural completion, MEP rough-in, finishes, TCO, CO)
- Provide a risk rating or watchlist recommendation with supporting rationale
Output
- Construction Loan Status Report containing:
- Loan summary (borrower, project, commitment, funded, available, maturity, extensions)
- Budget tracker with variance columns (budgeted, drawn-to-date, remaining, projected overrun/underrun)
- Draw approval summary for the current request (recommended amount, any holdbacks, conditions)
- Completion risk assessment (schedule, budget, contractor, market) with risk-level indicators
- Watchlist or escalation recommendation if applicable
- Action items and conditions precedent for the next draw
Quality Checks
- All dollar amounts tie between the draw request, SOV, inspector report, and loan balance
- Retainage calculations are arithmetically correct and match the loan agreement rate
- Lien waiver coverage is complete — no gaps between prior conditional and current unconditional waivers
- Interest reserve burn-rate projection confirms adequacy through projected completion plus lease-up (if applicable)
- Title update confirms no mechanic's liens or other intervening encumbrances
- Insurance certificates are current and coverage amounts meet loan agreement minimums
- Budget contingency adequacy is assessed relative to project stage and remaining risk
- Any data point sourced from borrower representations rather than independent verification is marked [VERIFY]
- Jurisdiction-specific requirements (lien law notice periods, retainage statutes, permit processes) are flagged with [VERIFY]