Project Risk Register
Table of Contents
- Workflow
- Common Patterns
- Risk Scoring Framework
- Guardrails
- Quick Reference
Risk Matrix (5×5 Probability×Impact):
Impact → 1 2 3 4 5
Prob ↓ Minimal Minor Moderate Major Severe
5 High │ Medium │ Medium │ High │ High │ Critical│
│ 5 │ 10 │ 15 │ 20 │ 25 │
4 │ Low │ Medium │ Medium │ High │ High │
│ 4 │ 8 │ 12 │ 16 │ 20 │
3 Medium │ Low │ Low │ Medium │ Medium │ High │
│ 3 │ 6 │ 9 │ 12 │ 15 │
2 │ Low │ Low │ Low │ Medium │ Medium │
│ 2 │ 4 │ 6 │ 8 │ 10 │
1 Low │ Low │ Low │ Low │ Low │ Medium │
│ 1 │ 2 │ 3 │ 4 │ 5 │
Risk Thresholds:
- Critical (≥20): Escalate to exec, immediate mitigation required
- High (12-19): Active management, weekly review, documented mitigation
- Medium (6-11): Monitor closely, monthly review, contingency plan
- Low (1-5): Accept or minimal mitigation, quarterly review
Example: Software Migration Project
| Risk ID |
Risk |
Prob |
Impact |
Score |
Owner |
Mitigation |
Contingency |
| R-001 |
Third-party API deprecated mid-project |
3 |
4 |
12 (Medium) |
Eng Lead |
Contact vendor for deprecation timeline |
Build abstraction layer for quick swap |
| R-002 |
Key engineer leaves during critical phase |
2 |
5 |
10 (Medium) |
EM |
Knowledge sharing, pair programming |
Contract backup engineer |
| R-003 |
Data migration takes 3× longer than estimated |
4 |
4 |
16 (High) |
Data Lead |
Pilot migration on 10% data first |
Extend timeline, reduce scope |
Workflow
Copy this checklist and track your progress:
Risk Register Progress:
- [ ] Step 1: Identify risks across categories
- [ ] Step 2: Assess probability and impact
- [ ] Step 3: Calculate risk scores and prioritize
- [ ] Step 4: Assign owners and define responses
- [ ] Step 5: Monitor and update regularly
Step 1: Identify risks across categories
Brainstorm what could go wrong using structured categories (technical, schedule, resource, external, scope). See Common Patterns for category checklists. Use resources/template.md for register structure.
Step 2: Assess probability and impact
Score each risk on probability (1-5: rare to almost certain) and impact (1-5: minimal to severe). Involve subject matter experts for accuracy. See Risk Scoring Framework for definitions.
Step 3: Calculate risk scores and prioritize
Multiply Probability × Impact for each risk. Plot on risk matrix (5×5 grid) to visualize risk profile. Focus mitigation on Critical/High risks first. See resources/methodology.md for advanced techniques like Monte Carlo simulation.
Step 4: Assign owners and define responses
For each High/Critical risk, assign named owner (not "team"), define mitigation (reduce probability), contingency (reduce impact), and triggers (when to activate contingency). See resources/template.md for response planning structure.
Step 5: Monitor and update regularly
Review risk register weekly (active projects) or monthly (longer projects). Update probabilities/impacts as context changes, add new risks, retire closed risks, track mitigation progress. See Guardrails for monitoring cadence.
Common Patterns
Risk categories (use for brainstorming):
- Technical risks: Technology failure, integration issues, performance problems, security vulnerabilities, technical debt, complexity underestimated
- Schedule risks: Dependencies delayed, estimation errors, scope creep, resource unavailability, critical path blocked
- Resource risks: Key person leaves, skill gaps, budget overrun, vendor/contractor issues, equipment unavailable
- External risks: Regulatory changes, market shifts, competitor actions, economic downturn, natural disasters, vendor bankruptcy
- Scope risks: Unclear requirements, changing priorities, stakeholder disagreement, gold-plating, mission creep
- Organizational risks: Lack of executive support, competing priorities, insufficient funding, organizational change, political conflicts
By project type:
- Software projects: Third-party API changes, dependency vulnerabilities, cloud provider outages, data migration issues, browser compatibility, scaling problems, security breaches
- Construction projects: Weather delays, material shortages, permit issues, labor strikes, soil conditions, cost overruns, safety incidents
- Product launches: Manufacturing delays, supply chain disruption, competitor launch, pricing miscalculation, market demand lower than expected, quality issues
- Organizational change: Employee resistance, communication breakdown, training inadequate, budget cuts, leadership turnover, cultural misalignment
By risk response type:
- Mitigate (reduce probability): Training, prototyping, process improvements, redundancy, quality checks, early testing
- Contingency (reduce impact if occurs): Backup plans, insurance, reserves (time/budget), alternative suppliers, rollback procedures
- Accept (do nothing): Low-score risks not worth mitigation cost, residual risks after mitigation
- Transfer (shift to others): Insurance, outsourcing, contracts (penalty clauses), warranties
Typical risk profile evolution:
- Project start: Many medium risks (uncertainty high), few critical (pre-mitigation)
- Mid-project: Critical risks mitigated to medium/low, new risks emerge (dependencies, integration)
- Near completion: Low risks dominate (most issues resolved), few high (last-minute surprises)
- Red flag: Risk score increasing over time (mitigation not working, new issues emerging faster than resolution)
Risk Scoring Framework
Probability Scale (1-5):
- 5 - Almost Certain (>80%): Expected to occur, historical data confirms, no mitigation in place
- 4 - Likely (60-80%): Probably will occur, similar projects had this issue, weak mitigation
- 3 - Possible (40-60%): May or may not occur, depends on circumstances, some mitigation in place
- 2 - Unlikely (20-40%): Probably won't occur, mitigation in place, low historical precedent
- 1 - Rare (<20%): Very unlikely, strong mitigation, no historical precedent
Impact Scale (1-5) - adjust dimensions for project context:
For Schedule Impact:
- 5 - Severe: >20% delay (e.g., 3-month project delayed 3+ weeks), miss critical deadline, cascading delays
- 4 - Major: 10-20% delay, miss milestone, affects dependent projects
- 3 - Moderate: 5-10% delay, timeline buffer consumed, no external impact
- 2 - Minor: <5% delay, absorbed within sprint/phase, minor schedule pressure
- 1 - Minimal: <1% delay or no delay, negligible schedule impact
For Budget Impact:
- 5 - Severe: >20% budget overrun, requires new funding approval, project viability threatened
- 4 - Major: 10-20% overrun, contingency exhausted, scope cuts required
- 3 - Moderate: 5-10% overrun, contingency partially used, no scope cuts
- 2 - Minor: <5% overrun, absorbed within budget flexibility
- 1 - Minimal: <1% overrun or no budget impact
For Scope/Quality Impact:
- 5 - Severe: Core functionality lost, customer-facing quality issue, regulatory violation
- 4 - Major: Important feature cut, significant quality degradation, customer complaints
- 3 - Moderate: Nice-to-have feature cut, minor quality issue, internal workarounds needed
- 2 - Minor: Edge case feature cut, cosmetic quality issue
- 1 - Minimal: No scope or quality impact
Composite Impact (when multiple dimensions affected):
- Use maximum of any single dimension (pessimistic, conservative)
- OR use weighted average: Schedule 40%, Budget 30%, Scope/Quality 30%
Example Scoring:
Risk: "Key engineer leaves mid-project"
- Probability: 2 (Unlikely - 20% based on tenure, satisfaction, retention rate)
- Impact Schedule: 4 (Major - 3-week delay to onboard replacement, knowledge transfer)
- Impact Budget: 2 (Minor - recruiter fees, some overtime)
- Impact Scope: 3 (Moderate - may cut advanced features)
- Composite Impact: 4 (take maximum: schedule impact is worst)
- Risk Score: 2 × 4 = 8 (Medium)
Guardrails
Ensure quality:
Identify risks proactively, not reactively: Run risk workshops before problems occur
- ✓ Brainstorm risks at project kickoff, use checklists (technical, schedule, resource, etc.)
- ❌ Add risks only after incidents occur (reactive)
Be specific, not vague: "Integration fails" is vague, "Vendor API rate limits block migration" is specific
- ✓ "Third-party payment gateway rejects 10% of transactions due to fraud rules"
- ❌ "Payment issues"
Separate probability and impact: Don't conflate "bad if it happens" with "likely to happen"
- ✓ Asteroid hits office: Prob=1 (rare), Impact=5 (severe), Score=5 (low priority)
- ❌ Conflating: "This is really bad so it must be high priority" (ignoring low probability)
Assign named owners, not teams: "Engineering team" is not accountable, "Sarah (Tech Lead)" is
- ✓ Owner: Sarah (Tech Lead), responsible for monitoring and activating contingency
- ❌ Owner: Engineering Team (diffused responsibility)
Define mitigation AND contingency: Mitigation reduces probability, contingency handles if it occurs anyway
- ✓ Mitigation: Prototype integration early (reduce prob). Contingency: Build abstraction layer for quick swap (reduce impact)
- ❌ Only mitigation, no backup plan
Update regularly: Stale risk register is worse than none (false confidence)
- ✓ Weekly review for active projects (High/Critical risks), monthly for longer projects
- ❌ Create register at kickoff, never update (probabilities/impacts change as project progresses)
Retire closed risks: Don't let register grow indefinitely, archive mitigated/irrelevant risks
- ✓ Mark risk "Closed" with resolution date, move to archive section
- ❌ Keep all risks forever (signal-to-noise ratio degrades)
Escalate critical risks immediately: Don't wait for weekly meeting if Critical risk emerges
- ✓ Prob=5 Impact=5 Score=25 → Escalate to exec same day, emergency mitigation
- ❌ Wait for scheduled review (risk could materialize)
Quick Reference
Resources:
- Quick start: resources/template.md - Risk register template with scoring table, response planning, monitoring log
- Advanced techniques: resources/methodology.md - Monte Carlo simulation, decision trees, sensitivity analysis, risk aggregation, earned value management
- Quality check: resources/evaluators/rubric_project_risk_register.json - Evaluation criteria
Success criteria:
- ✓ Identified 15-30 risks across all categories (technical, schedule, resource, external, scope, org)
- ✓ All High/Critical risks (score ≥12) have named owners, mitigation plans, and contingencies
- ✓ Risk scores differentiated (not all scored 6-9; use full 1-25 range)
- ✓ Mitigation and contingency plans are specific and actionable (not "monitor closely")
- ✓ Triggers defined for when to activate contingencies (quantifiable thresholds)
- ✓ Register updated regularly (weekly for active projects, monthly for longer projects)
- ✓ Risk profile matches project phase (high uncertainty at start, decreasing over time)
Common mistakes:
- ❌ Too few risks identified (<10) → incomplete risk picture, false confidence
- ❌ All risks scored medium (6-9) → not differentiated, unclear prioritization
- ❌ Vague risks ("things might not work") → not actionable
- ❌ No risk owners assigned → diffused accountability, mitigation doesn't happen
- ❌ Mitigation without contingency → no backup plan if mitigation fails
- ❌ Created once, never updated → stale data, risks evolve
- ❌ Only negative risks (threats) → missing opportunities (positive risks)
- ❌ Risk register separate from project plan → not integrated into workflow
When to use alternatives:
- Pre-mortem: When project hasn't started, want to imagine failure scenarios (complements risk register)
- FMEA (Failure Mode Effects Analysis): Manufacturing/engineering projects needing detailed failure analysis
- Monte Carlo simulation: When need probabilistic timeline/budget forecasting (use methodology.md)
- Decision tree: When risks involve sequential decisions with branch points
- Scenario planning: When risks are strategic/long-term (market shifts, competitor actions)
1---
2name: project-risk-register
3description: Identifies, assesses, and prioritizes project risks using probability-times-impact scoring (risk matrix), then assigns owners, mitigation plans, contingencies, and triggers to track risk evolution over the project lifecycle. Use when managing project uncertainty, building a risk register, conducting risk assessments, defining risk mitigation plans, or when user mentions risk register, risk management, probability-impact matrix, or asks "what could go wrong with this project?".
4---
5
6# Project Risk Register
7
8## Table of Contents
91. [Workflow](#workflow)
102. [Common Patterns](#common-patterns)
113. [Risk Scoring Framework](#risk-scoring-framework)
124. [Guardrails](#guardrails)
135. [Quick Reference](#quick-reference)
14
15**Risk Matrix (5×5 Probability×Impact):**
16
17```
18Impact → 1 2 3 4 5
19Prob ↓ Minimal Minor Moderate Major Severe
20
215 High │ Medium │ Medium │ High │ High │ Critical│
22 │ 5 │ 10 │ 15 │ 20 │ 25 │
234 │ Low │ Medium │ Medium │ High │ High │
24 │ 4 │ 8 │ 12 │ 16 │ 20 │
253 Medium │ Low │ Low │ Medium │ Medium │ High │
26 │ 3 │ 6 │ 9 │ 12 │ 15 │
272 │ Low │ Low │ Low │ Medium │ Medium │
28 │ 2 │ 4 │ 6 │ 8 │ 10 │
291 Low │ Low │ Low │ Low │ Low │ Medium │
30 │ 1 │ 2 │ 3 │ 4 │ 5 │
31```
32
33**Risk Thresholds:**
34- **Critical (≥20)**: Escalate to exec, immediate mitigation required
35- **High (12-19)**: Active management, weekly review, documented mitigation
36- **Medium (6-11)**: Monitor closely, monthly review, contingency plan
37- **Low (1-5)**: Accept or minimal mitigation, quarterly review
38
39**Example: Software Migration Project**
40
41| Risk ID | Risk | Prob | Impact | Score | Owner | Mitigation | Contingency |
42|---------|------|------|--------|-------|-------|------------|-------------|
43| R-001 | Third-party API deprecated mid-project | 3 | 4 | **12 (Medium)** | Eng Lead | Contact vendor for deprecation timeline | Build abstraction layer for quick swap |
44| R-002 | Key engineer leaves during critical phase | 2 | 5 | **10 (Medium)** | EM | Knowledge sharing, pair programming | Contract backup engineer |
45| R-003 | Data migration takes 3× longer than estimated | 4 | 4 | **16 (High)** | Data Lead | Pilot migration on 10% data first | Extend timeline, reduce scope |
46
47## Workflow
48
49Copy this checklist and track your progress:
50
51```
52Risk Register Progress:
53- [ ] Step 1: Identify risks across categories
54- [ ] Step 2: Assess probability and impact
55- [ ] Step 3: Calculate risk scores and prioritize
56- [ ] Step 4: Assign owners and define responses
57- [ ] Step 5: Monitor and update regularly
58```
59
60**Step 1: Identify risks across categories**
61
62Brainstorm what could go wrong using structured categories (technical, schedule, resource, external, scope). See [Common Patterns](#common-patterns) for category checklists. Use [resources/template.md](resources/template.md) for register structure.
63
64**Step 2: Assess probability and impact**
65
66Score each risk on probability (1-5: rare to almost certain) and impact (1-5: minimal to severe). Involve subject matter experts for accuracy. See [Risk Scoring Framework](#risk-scoring-framework) for definitions.
67
68**Step 3: Calculate risk scores and prioritize**
69
70Multiply Probability × Impact for each risk. Plot on risk matrix (5×5 grid) to visualize risk profile. Focus mitigation on Critical/High risks first. See [resources/methodology.md](resources/methodology.md) for advanced techniques like Monte Carlo simulation.
71
72**Step 4: Assign owners and define responses**
73
74For each High/Critical risk, assign named owner (not "team"), define mitigation (reduce probability), contingency (reduce impact), and triggers (when to activate contingency). See [resources/template.md](resources/template.md) for response planning structure.
75
76**Step 5: Monitor and update regularly**
77
78Review risk register weekly (active projects) or monthly (longer projects). Update probabilities/impacts as context changes, add new risks, retire closed risks, track mitigation progress. See [Guardrails](#guardrails) for monitoring cadence.
79
80## Common Patterns
81
82**Risk categories (use for brainstorming):**
83
84- **Technical risks**: Technology failure, integration issues, performance problems, security vulnerabilities, technical debt, complexity underestimated
85- **Schedule risks**: Dependencies delayed, estimation errors, scope creep, resource unavailability, critical path blocked
86- **Resource risks**: Key person leaves, skill gaps, budget overrun, vendor/contractor issues, equipment unavailable
87- **External risks**: Regulatory changes, market shifts, competitor actions, economic downturn, natural disasters, vendor bankruptcy
88- **Scope risks**: Unclear requirements, changing priorities, stakeholder disagreement, gold-plating, mission creep
89- **Organizational risks**: Lack of executive support, competing priorities, insufficient funding, organizational change, political conflicts
90
91**By project type:**
92
93- **Software projects**: Third-party API changes, dependency vulnerabilities, cloud provider outages, data migration issues, browser compatibility, scaling problems, security breaches
94- **Construction projects**: Weather delays, material shortages, permit issues, labor strikes, soil conditions, cost overruns, safety incidents
95- **Product launches**: Manufacturing delays, supply chain disruption, competitor launch, pricing miscalculation, market demand lower than expected, quality issues
96- **Organizational change**: Employee resistance, communication breakdown, training inadequate, budget cuts, leadership turnover, cultural misalignment
97
98**By risk response type:**
99
100- **Mitigate (reduce probability)**: Training, prototyping, process improvements, redundancy, quality checks, early testing
101- **Contingency (reduce impact if occurs)**: Backup plans, insurance, reserves (time/budget), alternative suppliers, rollback procedures
102- **Accept (do nothing)**: Low-score risks not worth mitigation cost, residual risks after mitigation
103- **Transfer (shift to others)**: Insurance, outsourcing, contracts (penalty clauses), warranties
104
105**Typical risk profile evolution:**
106- **Project start**: Many medium risks (uncertainty high), few critical (pre-mitigation)
107- **Mid-project**: Critical risks mitigated to medium/low, new risks emerge (dependencies, integration)
108- **Near completion**: Low risks dominate (most issues resolved), few high (last-minute surprises)
109- **Red flag**: Risk score increasing over time (mitigation not working, new issues emerging faster than resolution)
110
111## Risk Scoring Framework
112
113**Probability Scale (1-5):**
114- **5 - Almost Certain (>80%)**: Expected to occur, historical data confirms, no mitigation in place
115- **4 - Likely (60-80%)**: Probably will occur, similar projects had this issue, weak mitigation
116- **3 - Possible (40-60%)**: May or may not occur, depends on circumstances, some mitigation in place
117- **2 - Unlikely (20-40%)**: Probably won't occur, mitigation in place, low historical precedent
118- **1 - Rare (<20%)**: Very unlikely, strong mitigation, no historical precedent
119
120**Impact Scale (1-5) - adjust dimensions for project context:**
121
122**For Schedule Impact:**
123- **5 - Severe**: >20% delay (e.g., 3-month project delayed 3+ weeks), miss critical deadline, cascading delays
124- **4 - Major**: 10-20% delay, miss milestone, affects dependent projects
125- **3 - Moderate**: 5-10% delay, timeline buffer consumed, no external impact
126- **2 - Minor**: <5% delay, absorbed within sprint/phase, minor schedule pressure
127- **1 - Minimal**: <1% delay or no delay, negligible schedule impact
128
129**For Budget Impact:**
130- **5 - Severe**: >20% budget overrun, requires new funding approval, project viability threatened
131- **4 - Major**: 10-20% overrun, contingency exhausted, scope cuts required
132- **3 - Moderate**: 5-10% overrun, contingency partially used, no scope cuts
133- **2 - Minor**: <5% overrun, absorbed within budget flexibility
134- **1 - Minimal**: <1% overrun or no budget impact
135
136**For Scope/Quality Impact:**
137- **5 - Severe**: Core functionality lost, customer-facing quality issue, regulatory violation
138- **4 - Major**: Important feature cut, significant quality degradation, customer complaints
139- **3 - Moderate**: Nice-to-have feature cut, minor quality issue, internal workarounds needed
140- **2 - Minor**: Edge case feature cut, cosmetic quality issue
141- **1 - Minimal**: No scope or quality impact
142
143**Composite Impact** (when multiple dimensions affected):
144- Use **maximum** of any single dimension (pessimistic, conservative)
145- OR use **weighted average**: Schedule 40%, Budget 30%, Scope/Quality 30%
146
147**Example Scoring:**
148
149Risk: "Key engineer leaves mid-project"
150- Probability: 2 (Unlikely - 20% based on tenure, satisfaction, retention rate)
151- Impact Schedule: 4 (Major - 3-week delay to onboard replacement, knowledge transfer)
152- Impact Budget: 2 (Minor - recruiter fees, some overtime)
153- Impact Scope: 3 (Moderate - may cut advanced features)
154- **Composite Impact**: 4 (take maximum: schedule impact is worst)
155- **Risk Score**: 2 × 4 = **8 (Medium)**
156
157## Guardrails
158
159**Ensure quality:**
160
1611. **Identify risks proactively, not reactively**: Run risk workshops before problems occur
162 - ✓ Brainstorm risks at project kickoff, use checklists (technical, schedule, resource, etc.)
163 - ❌ Add risks only after incidents occur (reactive)
164
1652. **Be specific, not vague**: "Integration fails" is vague, "Vendor API rate limits block migration" is specific
166 - ✓ "Third-party payment gateway rejects 10% of transactions due to fraud rules"
167 - ❌ "Payment issues"
168
1693. **Separate probability and impact**: Don't conflate "bad if it happens" with "likely to happen"
170 - ✓ Asteroid hits office: Prob=1 (rare), Impact=5 (severe), Score=5 (low priority)
171 - ❌ Conflating: "This is really bad so it must be high priority" (ignoring low probability)
172
1734. **Assign named owners, not teams**: "Engineering team" is not accountable, "Sarah (Tech Lead)" is
174 - ✓ Owner: Sarah (Tech Lead), responsible for monitoring and activating contingency
175 - ❌ Owner: Engineering Team (diffused responsibility)
176
1775. **Define mitigation AND contingency**: Mitigation reduces probability, contingency handles if it occurs anyway
178 - ✓ Mitigation: Prototype integration early (reduce prob). Contingency: Build abstraction layer for quick swap (reduce impact)
179 - ❌ Only mitigation, no backup plan
180
1816. **Update regularly**: Stale risk register is worse than none (false confidence)
182 - ✓ Weekly review for active projects (High/Critical risks), monthly for longer projects
183 - ❌ Create register at kickoff, never update (probabilities/impacts change as project progresses)
184
1857. **Retire closed risks**: Don't let register grow indefinitely, archive mitigated/irrelevant risks
186 - ✓ Mark risk "Closed" with resolution date, move to archive section
187 - ❌ Keep all risks forever (signal-to-noise ratio degrades)
188
1898. **Escalate critical risks immediately**: Don't wait for weekly meeting if Critical risk emerges
190 - ✓ Prob=5 Impact=5 Score=25 → Escalate to exec same day, emergency mitigation
191 - ❌ Wait for scheduled review (risk could materialize)
192
193## Quick Reference
194
195**Resources:**
196- **Quick start**: [resources/template.md](resources/template.md) - Risk register template with scoring table, response planning, monitoring log
197- **Advanced techniques**: [resources/methodology.md](resources/methodology.md) - Monte Carlo simulation, decision trees, sensitivity analysis, risk aggregation, earned value management
198- **Quality check**: [resources/evaluators/rubric_project_risk_register.json](resources/evaluators/rubric_project_risk_register.json) - Evaluation criteria
199
200**Success criteria:**
201- ✓ Identified 15-30 risks across all categories (technical, schedule, resource, external, scope, org)
202- ✓ All High/Critical risks (score ≥12) have named owners, mitigation plans, and contingencies
203- ✓ Risk scores differentiated (not all scored 6-9; use full 1-25 range)
204- ✓ Mitigation and contingency plans are specific and actionable (not "monitor closely")
205- ✓ Triggers defined for when to activate contingencies (quantifiable thresholds)
206- ✓ Register updated regularly (weekly for active projects, monthly for longer projects)
207- ✓ Risk profile matches project phase (high uncertainty at start, decreasing over time)
208
209**Common mistakes:**
210- ❌ Too few risks identified (<10) → incomplete risk picture, false confidence
211- ❌ All risks scored medium (6-9) → not differentiated, unclear prioritization
212- ❌ Vague risks ("things might not work") → not actionable
213- ❌ No risk owners assigned → diffused accountability, mitigation doesn't happen
214- ❌ Mitigation without contingency → no backup plan if mitigation fails
215- ❌ Created once, never updated → stale data, risks evolve
216- ❌ Only negative risks (threats) → missing opportunities (positive risks)
217- ❌ Risk register separate from project plan → not integrated into workflow
218
219**When to use alternatives:**
220- **Pre-mortem**: When project hasn't started, want to imagine failure scenarios (complements risk register)
221- **FMEA (Failure Mode Effects Analysis)**: Manufacturing/engineering projects needing detailed failure analysis
222- **Monte Carlo simulation**: When need probabilistic timeline/budget forecasting (use methodology.md)
223- **Decision tree**: When risks involve sequential decisions with branch points
224- **Scenario planning**: When risks are strategic/long-term (market shifts, competitor actions)