INFOCOM Workflow
Use this as the project-management skill for an INFOCOM submission. Replace every date with the
current official timetable and work backwards from the abstract/metadata deadline (in late
July), which precedes the full-paper deadline by about a week. INFOCOM runs a single annual
summer deadline, so a missed cycle costs roughly a year — plan the calendar as tightly as the
paper.
INFOCOM is an IEEE ComSoc conference with no standing editor-in-chief and no
article-processing charge. Rotating leadership is the per-edition General Co-Chairs and TPC
Co-Chairs, appointed under ComSoc; the cost model is conference registration, and at least one
author must register for the paper to enter IEEE Xplore. Chairs rotate yearly; re-check the
organizing-committee page rather than carrying a name forward.
Milestones
- Venue fit: confirm INFOCOM over SIGCOMM/NSDI/MobiCom and confirm the paper is ready this
cycle (
infocom-topic-selection).
- Evidence lock: freeze the system model, theorems/proofs, simulator setup, baselines, and the
evaluation results.
- Abstract/metadata registration: enter real title, abstract (≤200 words), co-authors, and
topic tags into EDAS by the abstract deadline (INFOCOM 2026: 24 Jul 2025; 2027: 24 Jul 2026).
- Full-paper submission: upload the anonymized IEEEtran PDF (INFOCOM 2026: 31 Jul 2025; 2027:
31 Jul 2026), within the 10-page / ≤9-page-of-text budget.
- Early-reject checkpoint (if the cycle runs one): INFOCOM 2027 posts early-reject on 9 Oct
2026 — a mid-cycle signal, not a final verdict.
- Notification: final decision (INFOCOM 2026: 8 Dec 2025; 2027: 8 Dec 2026).
- Camera-ready: eCF copyright, PDF eXpress validation, IEEE Xplore-compliant PDF (INFOCOM 2026:
9 Jan 2026), plus author registration.
- Presentation: at least one author registers and presents at the conference.
Backward plan from the full-paper deadline
| Weeks out (heuristic) |
Networking-paper milestone |
| 12+ |
Problem formulated; system model and assumptions fixed; baselines chosen |
| 10 |
Theorems proved / protocol designed; simulator or testbed built |
| 8 |
Experiments/simulations complete; seeds and configs logged |
| 6 |
Analysis done; plots and tables built; proofs written up |
| 4 |
Full draft in IEEEtran; measured against the 9-page text boundary (refs excluded) |
| 3 |
Internal mock review by a reader from the other side (theory ↔ systems) |
| 2 |
Baselines hardened, related-work delta sharpened, page budget met |
| 1 |
Double-blind sweep on the PDF and metadata; abstract entered in EDAS |
| 0 |
Full paper on EDAS within the budget; five-paper cap re-checked |
These offsets are planning heuristics only — anchor every one to the current Call for Papers, never
to a previous cycle's calendar.
The single-summer calendar reality
INFOCOM runs one annual research deadline in late July, with notification in December and
the conference the following May. As of 2026-07-09, INFOCOM 2026 (Tokyo) is decided, so the
live next target is INFOCOM 2027 (Honolulu; abstract 24 Jul 2026, paper 31 Jul 2026). Two
planning consequences:
- A near-miss on the July deadline costs a full year at INFOCOM; a sibling flagship
(SIGCOMM/NSDI/MobiCom) or a journal (ToN/JSAC) may have a nearer date — factor that into routing
rather than idling.
- There is no rebuttal to plan for (traditionally): budget the pre-submission mock review as
the one and only chance to hear "your baseline is unfair" from a friend instead of a reviewer.
Failure modes by stage
- Evidence still moving at week 4 forces last-minute simulation nobody has audited — the classic
soundness reject.
- Discovering the paper is a page over at week 1 with appendices counted inside the nine pages —
a not-reviewed outcome that editing weeks earlier would have prevented.
- Skipping the cross-side mock review forfeits the chance to catch an unstated assumption
(theory reader) or an unrealistic topology (systems reader).
- Forgetting the five-paper cap on a group's submission sprint, so a sixth paper is dropped.
Coordination notes
- Assign one owner for the EDAS metadata/topic tags (they drive automated assignment) and another
for the double-blind sweep; shared ownership is how both slip.
- Archive the exact submitted PDF and the simulator/testbed configuration — the camera-ready must
match, and any released artifact must reproduce it.
Output format
[Current stage] idea / evidence / writing / abstract-registered / submitted / early-reject / accepted
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness>
[Risk register] <page budget / double-blind / evidence / baselines / author cap / registration>
[Owner map] <task -> person or role>
Source: brycewang-stanford/Awesome-Journal-Skills → INFOCOM-Skills/skills/infocom-workflow/SKILL.md
1---2name: infocom-workflow3description: Use when planning an IEEE INFOCOM project timeline from venue fit through the two-step EDAS abstract-then-paper registration, the early-reject checkpoint, the December notification, the IEEE Xplore camera-ready with PDF eXpress and eCF, and presentation, with backward-planning offsets for a networking paper and honest handling of the single-summer deadline.4---567# INFOCOM Workflow89Use this as the project-management skill for an INFOCOM submission. Replace every date with the10current official timetable and work backwards from the **abstract/metadata deadline** (in late11July), which precedes the full-paper deadline by about a week. INFOCOM runs a **single annual12summer deadline**, so a missed cycle costs roughly a year — plan the calendar as tightly as the13paper.1415INFOCOM is an IEEE ComSoc conference with **no standing editor-in-chief** and **no16article-processing charge**. Rotating leadership is the per-edition General Co-Chairs and TPC17Co-Chairs, appointed under ComSoc; the cost model is **conference registration**, and at least one18author must register for the paper to enter IEEE Xplore. Chairs rotate yearly; re-check the19organizing-committee page rather than carrying a name forward.2021## Milestones2223- **Venue fit:** confirm INFOCOM over SIGCOMM/NSDI/MobiCom and confirm the paper is ready this24 cycle (`infocom-topic-selection`).25- **Evidence lock:** freeze the system model, theorems/proofs, simulator setup, baselines, and the26 evaluation results.27- **Abstract/metadata registration:** enter real title, abstract (≤200 words), co-authors, and28 topic tags into EDAS by the abstract deadline (INFOCOM 2026: 24 Jul 2025; 2027: 24 Jul 2026).29- **Full-paper submission:** upload the anonymized IEEEtran PDF (INFOCOM 2026: 31 Jul 2025; 2027:30 31 Jul 2026), within the 10-page / ≤9-page-of-text budget.31- **Early-reject checkpoint (if the cycle runs one):** INFOCOM 2027 posts early-reject on 9 Oct32 2026 — a mid-cycle signal, not a final verdict.33- **Notification:** final decision (INFOCOM 2026: 8 Dec 2025; 2027: 8 Dec 2026).34- **Camera-ready:** eCF copyright, PDF eXpress validation, IEEE Xplore-compliant PDF (INFOCOM 2026:35 9 Jan 2026), plus author registration.36- **Presentation:** at least one author registers and presents at the conference.3738## Backward plan from the full-paper deadline3940| Weeks out (heuristic) | Networking-paper milestone |41|---|---|42| 12+ | Problem formulated; system model and assumptions fixed; baselines chosen |43| 10 | Theorems proved / protocol designed; simulator or testbed built |44| 8 | Experiments/simulations complete; seeds and configs logged |45| 6 | Analysis done; plots and tables built; proofs written up |46| 4 | Full draft in IEEEtran; measured against the 9-page text boundary (refs excluded) |47| 3 | Internal mock review by a reader from the other side (theory ↔ systems) |48| 2 | Baselines hardened, related-work delta sharpened, page budget met |49| 1 | Double-blind sweep on the PDF and metadata; abstract entered in EDAS |50| 0 | Full paper on EDAS within the budget; five-paper cap re-checked |5152These offsets are planning heuristics only — anchor every one to the current Call for Papers, never53to a previous cycle's calendar.5455## The single-summer calendar reality5657INFOCOM runs one annual research deadline in **late July**, with notification in **December** and58the conference the following **May**. As of 2026-07-09, INFOCOM 2026 (Tokyo) is decided, so the59live next target is **INFOCOM 2027** (Honolulu; abstract 24 Jul 2026, paper 31 Jul 2026). Two60planning consequences:6162- **A near-miss on the July deadline costs a full year** at INFOCOM; a sibling flagship63 (SIGCOMM/NSDI/MobiCom) or a journal (ToN/JSAC) may have a nearer date — factor that into routing64 rather than idling.65- **There is no rebuttal to plan for** (traditionally): budget the pre-submission mock review as66 the one and only chance to hear "your baseline is unfair" from a friend instead of a reviewer.6768## Failure modes by stage6970- **Evidence still moving at week 4** forces last-minute simulation nobody has audited — the classic71 soundness reject.72- **Discovering the paper is a page over at week 1** with appendices counted inside the nine pages —73 a not-reviewed outcome that editing weeks earlier would have prevented.74- **Skipping the cross-side mock review** forfeits the chance to catch an unstated assumption75 (theory reader) or an unrealistic topology (systems reader).76- **Forgetting the five-paper cap** on a group's submission sprint, so a sixth paper is dropped.7778## Coordination notes7980- Assign one owner for the EDAS metadata/topic tags (they drive automated assignment) and another81 for the double-blind sweep; shared ownership is how both slip.82- Archive the exact submitted PDF and the simulator/testbed configuration — the camera-ready must83 match, and any released artifact must reproduce it.8485## Output format8687```text88[Current stage] idea / evidence / writing / abstract-registered / submitted / early-reject / accepted89[Next official deadline] <date and source, or unknown>90[Critical path] <three tasks that determine readiness>91[Risk register] <page budget / double-blind / evidence / baselines / author cap / registration>92[Owner map] <task -> person or role>93```9495---9697**Source:** [`brycewang-stanford/Awesome-Journal-Skills`](https://github.com/brycewang-stanford/Awesome-Journal-Skills) → `INFOCOM-Skills/skills/infocom-workflow/SKILL.md`