VIS Workflow
Use this as the project-management skill for an IEEE VIS submission. Replace every date with the
current official timetable and work backwards from the abstract deadline — which precedes the
full-paper deadline and locks your author list. VIS publishes in IEEE TVCG, so plan for a likely
conditional-accept second round inside the review cycle, not just an accept/reject.
VIS is a conference whose full papers are journal articles: the conference has no standing
editor-in-chief, and the rotating analogue is the per-edition VIS Executive Committee, Overall Paper
Chairs, and the six Area Paper Chairs (verify the roster on the current organizing page — 待核实
beyond named chairs). The cost model is conference registration; at least one author presents.
Milestones
- Area fit: confirm VIS over a sibling venue and pick the primary area among the six
(
vis-topic-selection).
- Evidence lock: freeze the contribution type, the design rationale, the study/benchmark design,
and the supplemental video plan.
- Abstract: submit real title, abstract, final author list, primary area, and keywords by
the abstract deadline (VIS 2026: 21 March 2026).
- Full paper: upload the PDF (VIS 2026: 31 March 2026); title/abstract/PDF then freeze.
- Supplemental: finish and anonymize the video, code, and data in the one-week window (VIS 2026:
7 April 2026).
- First-round reviews: triage each comment by criterion (novelty, impact, evidence, methodology,
encoding rationale, reproducibility).
- Conditional accept (if issued): execute a revision plus a summary-of-changes, re-read by the
same reviewers against the required changes.
- Decision: archive reviews, response, and every submitted version.
- Acceptance: prepare the TVCG camera-ready, complete Open Practices disclosures, pursue the
Graphics Replicability Stamp on its own track, register, and present.
Backward plan from the paper deadline
| Weeks out (heuristic) |
Visualization-paper milestone |
| 10+ |
Contribution type fixed; data/task abstraction and design rationale settled |
| 8 |
Technique/system implemented; study or benchmark designed; preregistration filed if used |
| 6 |
Study run / benchmark complete; effect sizes and CIs computed; figures drafted |
| 4 |
Full draft in the VGTC/TVCG template; supplemental video shot |
| 3 |
Internal mock review by a visualization reader |
| 2 |
Encoding rationale hardened, related-work delta sharpened, 9-page budget met |
| 1 |
Abstract submitted with final authors; anonymity sweep on PDF + video (if double-blind) |
| 0 |
Full PDF uploaded; supplemental finished and anonymized in its extra week |
These offsets are planning heuristics only — anchor every one to the current call, never to a
previous cycle's calendar.
The annual-cycle reality
VIS runs a single annual full-paper cycle. Two planning consequences:
- A conditional accept has a hard second-round window. Under-budgeting the revision turns a
winnable R&R into a reject; treat the required changes as a scored deadline, not a formality.
- Missing the annual deadline costs roughly a year at VIS; a sibling venue (EuroVis, PacificVis)
or the TVCG journal track may have a nearer date — factor that into routing rather than idling.
Failure modes by stage
- Evidence still moving at week 4 forces last-minute studies nobody has audited — the classic
methodology reject in the making.
- Leaving the video to the final week wastes VIS's extra supplemental week and ships an
unpolished or identity-leaking video that reviewers judge harshly.
- Skipping the mock review forfeits the one chance to hear "your encoding is not justified" from
a friend instead of a reviewer.
- Treating a conditional accept as an accept and under-budgeting the revision turns it into a
rejection.
- Adding an author after the abstract deadline — not permitted; finalize authorship early.
Coordination notes
- Assign one owner for the supplemental video/code and another for the anonymity sweep; shared
ownership is how both slip.
- Archive the exact submitted PDF, supplemental, and (later) summary-of-changes — the second round
must quote them precisely and, if double-blind, stay anonymous through phase one.
Output format
[Current stage] idea / evidence / writing / abstract / submitted / conditional accept / accepted
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness>
[Risk register] <page budget / anonymity / evidence / encoding rationale / video / second round>
[Owner map] <task -> person or role>
Source: brycewang-stanford/Awesome-Journal-Skills → VIS-Skills/skills/vis-workflow/SKILL.md
1---2name: vis-workflow3description: Use when planning an IEEE VIS project timeline from area fit through the abstract and full-paper deadlines, the two-phase review, the conditional-accept second round, the IEEE TVCG camera-ready, the Graphics Replicability Stamp, and presentation, with backward-planning offsets for a visualization paper and honest handling of the annual cycle and the second-round revision window.4---567# VIS Workflow89Use this as the project-management skill for an IEEE VIS submission. Replace every date with the10current official timetable and work backwards from the **abstract** deadline — which precedes the11full-paper deadline and locks your author list. VIS publishes in **IEEE TVCG**, so plan for a likely12**conditional-accept second round** inside the review cycle, not just an accept/reject.1314VIS is a conference whose full papers are journal articles: the **conference** has no standing15editor-in-chief, and the rotating analogue is the per-edition VIS Executive Committee, Overall Paper16Chairs, and the six Area Paper Chairs (verify the roster on the current organizing page — **待核实**17beyond named chairs). The cost model is conference registration; at least one author presents.1819## Milestones2021- **Area fit:** confirm VIS over a sibling venue and pick the **primary area** among the six22 (`vis-topic-selection`).23- **Evidence lock:** freeze the contribution type, the design rationale, the study/benchmark design,24 and the supplemental video plan.25- **Abstract:** submit real title, abstract, **final author list**, primary area, and keywords by26 the abstract deadline (VIS 2026: 21 March 2026).27- **Full paper:** upload the PDF (VIS 2026: 31 March 2026); title/abstract/PDF then freeze.28- **Supplemental:** finish and anonymize the video, code, and data in the one-week window (VIS 2026:29 7 April 2026).30- **First-round reviews:** triage each comment by criterion (novelty, impact, evidence, methodology,31 encoding rationale, reproducibility).32- **Conditional accept (if issued):** execute a revision plus a summary-of-changes, re-read by the33 same reviewers against the required changes.34- **Decision:** archive reviews, response, and every submitted version.35- **Acceptance:** prepare the TVCG camera-ready, complete Open Practices disclosures, pursue the36 Graphics Replicability Stamp on its own track, register, and present.3738## Backward plan from the paper deadline3940| Weeks out (heuristic) | Visualization-paper milestone |41|---|---|42| 10+ | Contribution type fixed; data/task abstraction and design rationale settled |43| 8 | Technique/system implemented; study or benchmark designed; preregistration filed if used |44| 6 | Study run / benchmark complete; effect sizes and CIs computed; figures drafted |45| 4 | Full draft in the VGTC/TVCG template; supplemental video shot |46| 3 | Internal mock review by a visualization reader |47| 2 | Encoding rationale hardened, related-work delta sharpened, 9-page budget met |48| 1 | Abstract submitted with final authors; anonymity sweep on PDF + video (if double-blind) |49| 0 | Full PDF uploaded; supplemental finished and anonymized in its extra week |5051These offsets are planning heuristics only — anchor every one to the current call, never to a52previous cycle's calendar.5354## The annual-cycle reality5556VIS runs a single annual full-paper cycle. Two planning consequences:5758- **A conditional accept has a hard second-round window.** Under-budgeting the revision turns a59 winnable R&R into a reject; treat the required changes as a scored deadline, not a formality.60- **Missing the annual deadline costs roughly a year** at VIS; a sibling venue (EuroVis, PacificVis)61 or the **TVCG journal track** may have a nearer date — factor that into routing rather than idling.6263## Failure modes by stage6465- **Evidence still moving at week 4** forces last-minute studies nobody has audited — the classic66 methodology reject in the making.67- **Leaving the video to the final week** wastes VIS's extra supplemental week and ships an68 unpolished or identity-leaking video that reviewers judge harshly.69- **Skipping the mock review** forfeits the one chance to hear "your encoding is not justified" from70 a friend instead of a reviewer.71- **Treating a conditional accept as an accept** and under-budgeting the revision turns it into a72 rejection.73- **Adding an author after the abstract deadline** — not permitted; finalize authorship early.7475## Coordination notes7677- Assign one owner for the supplemental video/code and another for the anonymity sweep; shared78 ownership is how both slip.79- Archive the exact submitted PDF, supplemental, and (later) summary-of-changes — the second round80 must quote them precisely and, if double-blind, stay anonymous through phase one.8182## Output format8384```text85[Current stage] idea / evidence / writing / abstract / submitted / conditional accept / accepted86[Next official deadline] <date and source, or unknown>87[Critical path] <three tasks that determine readiness>88[Risk register] <page budget / anonymity / evidence / encoding rationale / video / second round>89[Owner map] <task -> person or role>90```9192---9394**Source:** [`brycewang-stanford/Awesome-Journal-Skills`](https://github.com/brycewang-stanford/Awesome-Journal-Skills) → `VIS-Skills/skills/vis-workflow/SKILL.md`