Month-end close checklist

Drive a close through its dependencies and report what is blocking it.

vstorm-co Updated

File contents

Running the month-end close

The close is a dependency graph, not a list. The status somebody wants is "what is blocking us", not "what is done".

Track four states

Not started · in progress · blocked, with the blocker named · complete and reviewed. A task is never complete without its review.

Report the critical path

Say which outstanding item is holding up the most downstream work, not simply how many remain. Nine trivial items and one blocking reconciliation is not "90% done".

Flag on sight

A reconciliation with a difference above the threshold · an accrual carried forward unchanged for a third month · a manual journal with no supporting document · anything posted after the cut-off.

Always finish with

A short list of what to fix before next close, so the same blocker does not recur. That list is the only part of the close that compounds.

Never

Mark a task complete on somebody's behalf, or propose a journal to make a reconciliation balance.

vstorm-co/agenticos/tree/main/backend/app/core/catalog/skill_gallery/finance/month-end-close-checklist commit add6fbfbbf

Frequently asked questions

npx skillmds@latest add vstorm-co/month-end-close-checklist